14
Section 4.4 of Annex 7 specifies that Vector products should be thematically attributed with a range [...]
Firstly, all features that can help and are deemed relevant to ensure that for future change detection [...]
13/08/2019
Beantwortet
13
While section 4.6 of Annex 7 specifies a general CLC+ backbone thematic accuracy of 90 %, section 4.4.1 [...]
One specification does not exclude the other, but in this case, section 4.4.1 of Annex 7 provides further [...]
13/08/2019
Beantwortet
12
What is exactly meant with the award criteria “Completeness and the level of detail of the workflow information [...]
In essence all elements of information that are essential to be able to reproduce the process and obtain [...]
13/08/2019
Beantwortet
11
Which is the date of reference in case of changing areas?
In principle, the reference year is 2018 for the satellite input imagery, and as closely as possible [...]
13/08/2019
Beantwortet
10
Which texture parameter is expected from the VHR coverage?
It is up to tenderers to choose the most suited texture parameter to improve the classification.
13/08/2019
Beantwortet
9
As the use of VHR2018 is mandatory in the CLC + production, will it be supplied to process the pilot [...]
Yes, the VHR2018 coverage will be available for CLC+ Backbone.
13/08/2019
Beantwortet
8
In page 11 it is stated that only the management of the processing and storage shall be taken into account [...]
The EEA is currently assessing options for a CLMS wide processing, storage and delivery platform (such [...]
13/08/2019
Beantwortet
7
Section 1.4.8 of the Tender Specifications asks that “national projection products, where those are part [...]
National projection products are considered an integral part of production and are expected as deliverables [...]
12/08/2019
Beantwortet
6
Could you please confirm if we understood the following correctly? 1. We need to create an account on [...]
You are right in your assumptions in both instances.
12/08/2019
Beantwortet
5
The exclusion criteria do not state any exclusion of EAGLE group members. Can you please clarify whether [...]
It is not possible at this stage to give a definite answer. The decision of whether to reject a tenderer [...]
12/08/2019
Beantwortet