Details zur Ausschreibung

Titel:
Rahmenvertrag – Technische und logistische Unterstützung für die Aktivitäten der...
Öffentlicher Auftraggeber:
European Commission, DG Migration and Home Affairs (HOME)
Datum der Veröffentlichung im TED:
07/05/2019
Frist für den Eingang von Angeboten:
27/06/2019
Status:
Geschlossen
Filter-Parameter anzeigen

Results per page: 10 | 25 | 50 66 Fragen found, displaying 51 to 60.[First/Prev] 1, 2, 3, 4, 5, 6, 7 [Next/Last]
# Frage Antwort Datum der letzten Veröffentlichung Status
8
Regarding the first 3 lines, i.e. the following: 'Management fee for organisation of event to prepare [...]
Your understanding is correct.
17/05/2019
3
Regarding the following: '- 1 stand to be installed in a building of the contracting authority dimensions [...]
The storage surface is included in the 30 sqm.
17/05/2019
4
Regarding the following: '15 meters long zig zag exhibition with 15 photos with description plate for [...]
The text on the plate shall be provided by the Contracting Authority, while the plate itself shall be [...]
17/05/2019
41
Thank you for your prompt reply, nevertheless, there is still some room for clarification. Please can [...]
A) Please refer to section 4 “contract award criteria”, criterion 1, which refers to the elements of [...]
12/06/2019
63
the answer to question 13 is: "Could you please clarify why the contractor would send its staff and which [...]
The contracting authority does not foresee the presence of the contractor’s staff during an event. The [...]
20/06/2019
64
the price of this item is supposed to be at "real price". please indicate the amount to be completed [...]
Please refer to answer 59.
20/06/2019
59
there are 2 cells, we do not know how to proceed to encode. Please adivse. if "Real cost": shall we put [...]
In the list of prices, in the column “Unit”, when it says real cost, you shall not indicate anything [...]
20/06/2019
24
There is no unit applied to this budget line. Should we consider it to be "real price + % of total price [...]
Price per Unit per day. Corrigendum of the price list will follow.
29/05/2019
20
we believe it is not possible to have a local network of own or identified providers in each EU country [...]
If the Contracting authority requests the presence of the event coordinator or any other profile as defined [...]
28/05/2019
22
We have noticed that no percentage of total cost is applied to this budget line. Could you clarify if [...]
The price of a venue with equipment included is on real cost base. No margin should be applied.
29/05/2019