582
|
Given that we are one week before the final submission of the tenders, while numerous answers to questions [...]
|
The deadline for submission remains as announced in the last Q&A and as published in the latest corrigendum [...]
|
06/05/2020
|
|
581
|
The current financial evaluation questionnaire reflects costing/pricing in the template for the 83% of [...]
|
The financial evaluation will be done on the elements included in the Financial Evaluation Questionnaire [...]
|
06/05/2020
|
|
580
|
Please clarify if the average numbers per profile for 2017 -2019 to be given in the Table provided by [...]
|
Both tables need to respect the minimum required number of profiles. In the summary table the tenderers [...]
|
06/05/2020
|
|
579
|
In the sheet ‘Lot 2 - FP price (C)’ there is error in the cells C35 and C73. Cell C35 can be up to 3000 [...]
|
Your understanding is correct. The updated file is available in the document library of e-Tendering.
|
06/05/2020
|
|
578
|
In both Lot 2 and Lot 3 we have a KPI for Incident Acknowledgement time (i.e. KPI-29 / KPI-26), that [...]
|
We confirm that the starting point of KPIs 27 and 30 under Lot 2 and 3 it is the "Time of assignment [...]
|
06/05/2020
|
|
577
|
With reference to Annex 4 - Service Requirements, section 3.1.2, definition of Products (as per the General [...]
|
We confirm that at this stage the information on unit price per product, delivery, installation and assembly [...]
|
06/05/2020
|
|
576
|
Is there a minimum requirement for on-site work in Lot 4?
|
The minimum requirements per profiles and security requirements are set in Annex 1 Description of services [...]
|
06/05/2020
|
|
575
|
Could you please confirm that the Legal Entity Form along with its attachments as well as the Financial [...]
|
The tenderers may upload those form in section "other". Please make sure to upload all the documents [...]
|
06/05/2020
|
|
574
|
(a) Is there a conflict of interest when a contractor of EXTRA is also a bidder (contractor or subcontractor [...]
|
a) Please refer to questions 102 and 217. b) We confirm in case the EXTRA contractor with conflict of [...]
|
06/05/2020
|
|
573
|
In case that a tenderer rely on the capacities of other entities where the latter will perform the works [...]
|
It is up to the tenderers to decide to take a company as subcontractor or just rely on their capacity [...]
|
06/05/2020
|
|