109
"1. Downward price revision to apply in case of change in resource profile or scope of work is reduced [...]
The price revision terms for this framework contract are defined in Article I.5.2 of the Special Conditions [...]
19/07/2018
Απαντήθηκε
106
1. Should expenses incurred (if any) be estimated and included in the pricing? 2. Instead of a price [...]
1. Please note that reimbursement of expenses is not applicable to this framework contract as defined [...]
19/07/2018
Απαντήθηκε
112
1. What is the difference between Intramural & Extramural pricing? 2. What components should form [...]
In regards to “1. Price Element 1: Resource pricing matrix” described in “2.9.1 Pricing Model”, the “ [...]
19/07/2018
Απαντήθηκε
57
A non-exhaustive list of IT products that may be taken over by the Contractor is listed in Technical [...]
Technical Annex B (IT Product listing) states that “This Annex complements the tender specification and [...]
04/07/2018
Απαντήθηκε
65
According to Annex VII, e-submission application guide, section 1.2 (page 3), could you please clarify [...]
Alternative B) is right, so only the declaration on honour (Annex III) and tender report (from eSubmission [...]
05/07/2018
Απαντήθηκε
80
According to Annex VIII. Tenderer shall provide Financial identification form. This document must be [...]
Financial identification form is needed only for one bank account. The tenderer should choose the bank [...]
09/07/2018
Απαντήθηκε
53
According to section “3.2.3 Technical and professional capacity”, page 63 of the Tender specifications [...]
The reference (“A short description detailing the methodologies / tools / technologies / IT products [...]
04/07/2018
Απαντήθηκε
50
According to the document, the situation in force at the ECDC is likely subject to change. Our company [...]
ECDC will continue to use Sparx Enterprise Architect for the modelling of Enterprise Architecture, “stakeholder [...]
04/07/2018
Απαντήθηκε
39
According to the Economic and financial selection criteria, tenderer must have for each of the past three [...]
Indeed, the selection criteria applies to the consortium as a whole, not per consortium member.
28/06/2018
Απαντήθηκε
122
According to the eSubmission guide the original hand signed tender report and/or hand signed declaration [...]
Please note that ECDC's new address is: Gustav III:s Boulevard 40, 16973 Solna, Sweden.
19/07/2018