Λεπτομέρειες πρόσκλησης υποβολής προσφορών

Τίτλος:
Σύμβαση πλαίσιο - Τεχνική και υλικοτεχνική υποστήριξη των δραστηριοτήτων της Γεν...
Αναθέτουσα αρχή:
European Commission, DG Migration and Home Affairs (HOME)
Ημερομηνία δημοσίευσης στο TED:
07/05/2019
Προθεσμία παραλαβής προσφορών:
27/06/2019
Κατάσταση:
Έχει κλείσει
Εμφάνιση παραμέτρων φίλτρου

Results per page: 10 | 25 | 50 66 Ερωτήματα found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4, 5, 6, 7 [Next/Last]
# Ερώτημα Απάντηση Ημερομηνία τελευταίας δημοσίευσης Κατάσταση
66
flat rate of EUR 15 000 is without technical Equipment. 400 chairs are requested. chairs are furniture [...]
The flat rate of 15 000 EUR does not include the price of the 400 chairs. The bidder shall include the [...]
20/06/2019
65
in case study 3 it is stated: "Venue without equipment included (meeting room and cocktail networking [...]
For the case study 3, the bidder shall consider that the room is rented at the Crown Plaza without equipment [...]
20/06/2019
64
the price of this item is supposed to be at "real price". please indicate the amount to be completed [...]
Please refer to answer 59.
20/06/2019
63
the answer to question 13 is: "Could you please clarify why the contractor would send its staff and which [...]
The contracting authority does not foresee the presence of the contractor’s staff during an event. The [...]
20/06/2019
62
please confirm the value to be indicated since the price is "Reimbursed according to EC mission guide [...]
The bidder shall not fill in the unit price as it will be reimbursed according to EC mission guide.
20/06/2019
61
Concerning case study 3: is the contractor requested to provide networking cocktail on 8 December ?
No case study refers to the date of 8 December. If the question refers to case study 3, the bidder shall [...]
20/06/2019
60
are we free to make a recommandation of the best approach? Pleas confirm that it is not mandatory to [...]
Please refer to answer 48. The bidder is not requested to provide a concept different from the one foreseen [...]
20/06/2019
59
there are 2 cells, we do not know how to proceed to encode. Please adivse. if "Real cost": shall we put [...]
In the list of prices, in the column “Unit”, when it says real cost, you shall not indicate anything [...]
20/06/2019
58
may we kinldy ask the contracting authority to provide all tenderers with a document with this column [...]
Please add a column to the word version of the list of prices.
20/06/2019
57
are we right to assume that the price of the three management fee Belgium/oustiste Belgium/oustide EU [...]
If the Contracting authority requests the presence of the event coordinator or any other profile as defined [...]
20/06/2019