# Ερώτημα Απάντηση Ημερομηνία τελευταίας δημοσίευσης Κατάσταση
17
In annex 5, Can you confirm that, in the following sentence: “1) To submit a tender as a partner in the [...]
The group of partners relates only to the tenderers and not subcontractors. Since we have no access to [...]
23/10/2019
16
Where exactly should the tender include the proportion of the contract that will be subcontracted? In [...]
Financial tender would probably be the best place for it.
23/10/2019
15
Should we receive some documents concerning footnote 2 and 3 in the SAL “Reference will be provided as [...]
The security aspect letter is provided at this stage as an example only. The official version including [...]
23/10/2019
14
In the context of subcontractors, could you please specify what you mean with "whose capacity is necessary [...]
The declaration of honour Annex IV has to be provided by subcontractors whose capacity is needed to fulfil [...]
23/10/2019
13
Do members of an external consultancy board not involved in the execution of the tasks have to sign Annex [...]
If the contribution of an external consultancy board is financed by the contract resulting from this [...]
22/10/2019
12
Could you please let us know which member of the subcontracting company has to sign Annex 6a: an authorised [...]
The letter of intent for subcontractor should be signed by person legally authorised to represent the [...]
22/10/2019
11
Could you please tell us if the requested photocopy of the notice of appointment of the persons authorised [...]
The document can be provided in the national language of the partner/subcontractor, but of course if [...]
21/10/2019
10
Can a subcontractor whose competences are not necessary to fulfil the selection criteria act as Work [...]
The tender specifications do not refer to work packages, hence the question on work package leaders is [...]
21/10/2019
9
Annex 6a states: […] Declares hereby that, in case the contract is awarded to [name of the tenderer], [...]
The name of the tenderer in Annex 6a should contain the names of all partners participating in the tender [...]
18/10/2019
8
Shall identified subcontractors who have to sign Annex 4 also sign Annex 3 (admin. ID form) ?
The subcontractors do not need to sign Annex 3. In accordance with the Checklist of documents to be submitted [...]