1
|
Due to COVID-19 and measures taken by EU states' governments, we are applying a work-from-home approach [...]
|
The services to be procured under this procedure are needed to replace as soon as possible the services [...]
|
21/04/2020
|
|
2
|
1. Regarding the Datacentre move, EMSA shall perform a list of tests to qualify that the reboot on the [...]
|
Yes, reboot tests are requested as part of the all-inclusive move. EMSA Personnel might assist in this [...]
|
22/04/2020
|
|
3
|
2. Some weeks preceding the move, all applications that use EMSA BCF (Madrid) as the main site will be [...]
|
Yes, site will be emptied of its applications by EMSA Team before the move will start.
|
22/04/2020
|
|
4
|
3. What’s the maximum time that EMSA BCF (Madrid) systems could remain shutdown to perform the move?
|
EMSA BCF systems should not stay in shutdown for more than 10 calendar days. The longer the shutdown [...]
|
22/04/2020
|
|
5
|
4. All rack equipment’s (except Oracle Exadata and Netapp array) have active support contracts that cover [...]
|
Equipment has active support contracts, which however does not cover for damages provoked by a move – [...]
|
22/04/2020
|
|
6
|
5. The Oracle Exadata X5-2, Netapp storage array and “TESTA” rack shall be moved on different and segregated [...]
|
Not necessarily.
|
22/04/2020
|
|
7
|
6. Does TESTA rack requires any specialized professional services?
|
As explained in the Tender Specifications (section 2.1, page 6), TESTA rack might have to be moved without [...]
|
22/04/2020
|
|
8
|
7. How many racks shall be provided by us on our Datacentre to EMSA equipment’s (excluding EXADATA and [...]
|
EMSA has its own racks, and doesn’t need any rack provided by the Tenderer. EMSA own racks shall be moved [...]
|
22/04/2020
|
|
9
|
8. Does CCTV monitoring the cage will be provided by EMSA, regarding this quote on Specification Document [...]
|
Yes – the Tenderer shall confirm that it is possible for EMSA to activate its own camera monitoring system [...]
|
22/04/2020
|
|
10
|
9. What requirements are requested to access control for the cage?
|
Tenderer shall propose its control measures available for accessing the datacentre and the cage.
|
22/04/2020
|
|