131
|
"For Third country citizen, confirm travel document validity, registration in the EES database, and confirm [...]
|
Annex II_2 ToR section 1.1. Annex II_2 ToR section 1.1. The problem "The innovation pursued by the pilot [...]
|
14/09/2020
|
|
130
|
Your statement in the procurement reads: The ‘core-system’ shall be able to manage the concurrent deployment [...]
|
Regarding Phase Two implementation, the resolution time for scaling up should be within a month of a [...]
|
14/09/2020
|
|
129
|
“...Outside these hours, technical support shall be provided within 4 hours. “- Can you please confirm [...]
|
Affirmative, support needs to be on site in that time frame. Refer to Annex II_1_and_2 Section 3.4 c) [...]
|
14/09/2020
|
|
128
|
Please clarify the following further. The tender documentation discusses the use of a total of TWO eGates [...]
|
Annex II_2 section 2.2 "The core-system shall consist of a set of FOUR self registration kiosks and TWO [...]
|
14/09/2020
|
|
127
|
Question 1: Your reply is not 100% clear. Please elaborate your understanding of the difference between [...]
|
Please refer to Annex II_2 ToR, Section 2.3 Use cases applicable for both ENTRY and EXIT systems actions [...]
|
14/09/2020
|
|
126
|
Please confirm that when bidders propose for both lots, they may use the same employee for both Project [...]
|
Annex I Tender Specifications section III.4.3 Technical and professional capacity and Annex II 1_and_ [...]
|
14/09/2020
|
|
125
|
The two Sections seem to be contradicting. Please confirm that the statement in section 4.2.a prevails [...]
|
Negative, Phase 2 should start T0+6 months at the latest under specific request by Frontex once the Phase [...]
|
14/09/2020
|
|
124
|
Section 3.3.c describes the Functional Requirements for “Verification gate/corridor tasks for EU and [...]
|
Please, see Annex II 1_and_2 section 2.3. Use cases applicable for both ENTRY and EXIT a. NOT registered [...]
|
14/09/2020
|
|
123
|
Will the Host country be responsible for any civil works that would be required, such as floor preparation [...]
|
Please see Annex II 1_and_2 section 4.5. Working Conditions "The Host will provide physical space for [...]
|
14/09/2020
|
|
122
|
"For Third country citizen, confirm travel document validity, registration in the EES database, and confirm [...]
|
This is correct, touchless functionality is not necessary for registration tablets. Please refer to Annex [...]
|
14/09/2020
|
|