Call for tenders' details

Title:
Housing/Hosting Services for a Business Continuity DataCentre
Contracting authority:
European Maritime Safety Agency
TED publication date:
06/04/2020
Time limit for receipt of tenders:
11/05/2020
Status:
Closed
Hide filter parameters
Filter parameters


Results per page: 10 | 25 | 50 47 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4, 5 [Next/Last]
# Question Answer Last publication date Status
47
33. Do EMSA BCF has access conditions to take the racks completed or need to be in parts (ex: weight [...]
The current EMSA BCF hosting site has the access conditions to move the complete racks.
05/05/2020
46
32. The move includes cables?
Yes all cables should be moved and re-installed to be re-used in the new hosting center.
05/05/2020
45
31. The move of the systems/equipment is just in one wave or EMSA need more than one wave to do the move [...]
The move shall be performed in as less time as possible in order to minimise the risk for EMSA of being [...]
05/05/2020
44
30. In any circumstances the move includes moving all the systems/equipment but not the rack?
Racks shall be moved together with the other equipment, and shall be re-installed to be re-used in the [...]
05/05/2020
43
29. The system/equipment in the origin site has all the cables (energy, networking, etc.) tagged or is [...]
It is part of the service to tag it.
05/05/2020
42
28. Is it possible to refer the validity of the contract of this systems/equipment and the entity that [...]
After the award of the contract, a kick off meeting will be held to review the plan for the move, and [...]
05/05/2020
41
27. It’s possible to have Serial Number of each system/equipment in scope?
After the award of the contract, a kick off meeting will be held to review the plan for the move, and [...]
05/05/2020
40
26. What is the scope of EMSA team in this process?
EMSA Team will assist at the beginning with the shutdown phase (remotely), and then it will assist again [...]
05/05/2020
39
25. It is possible to have remote access to the systems/equipment located in EMSA BCF through EMSA DC [...]
Yes – after the contract award.
05/05/2020
38
24. We assume that EMSA will guaranty data recovery mechanisms (backups) and have operational recovery [...]
Yes
05/05/2020