Call for tenders' details

Title:
Supply, installation and maintenance of 2 battery storage systems - 2 lots.
Contracting authority:
European Commission, Joint Research Centre (JRC)
TED publication date:
31/07/2015
Time limit for receipt of tenders:
28/09/2015
Status:
Closed
Hide filter parameters
Filter parameters


Results per page: 10 | 25 | 50 53 Questions found, displaying 26 to 50.[First/Prev] 1, 2, 3 [Next/Last]
# Question Answer Last publication date Status
26
Referring to the procedure we ask for an extension of one month for the presentation of the tenders.
Please see the answer to the question 24
07/09/2015
27
What is the meaning of the term "Smooth" in relation to transitions between operations on-grid and off-grid [...]
"Smooth" means that the transition will be done without interruptions.
07/09/2015
28
Considering the need for air conditioning, is the degree of protection IP23 defined as the minimum acceptable [...]
IP23 is the requirement for acceptance and therefore the minimum acceptable protection for the container [...]
07/09/2015
29
Does 25 ° C refer to the outside temperature or to that of the equipment?
It refers to ambient temperature of the room(s) or container(s) where the different pieces of equipment [...]
07/09/2015
30
Is it possible to have a more detailed description of the 3 operating modes mentioned?
More information are available within the "explanatory and requirements details", page 7, 2nd point.
07/09/2015
31
Given the temperature range required, is it correct to say that the climate control system should be [...]
Yes, it is correct to consider that climate control system is required. Climate control system shall [...]
07/09/2015
32
Is it possible to have a description of critical and non-critical loads as well as the management mode [...]
Critical loads include specific systems that will remain operational during an outage. Typical "critical [...]
07/09/2015
33
In the penultimate paragraph, what is meaning of the term "Smooth" relatively to connections and disconnections [...]
Please see the response to question 27
09/09/2015
34
In the formula for the calculation of liquid damages, the value of "d" is given by the sum of the total [...]
"d" refers to each duration mentioned in the article I.2.3. (respectively: 5 months, 2 years, twelve [...]
09/09/2015
35
Given that the two months of delivery of the materials are essential (see the answer to question 22), [...]
Please refer to the supplementary answer to the question 22
09/09/2015
36
Chiediamo altresì di confermare l’assenza di penali in caso di consegna del BESS oltre il limite dei [...]
Se il contraente non adempie gli obblighi contrattuali entro i termini fissati dal contratto, ferma restando [...]
14/09/2015
37
On page 4 of the technical specifications, it indicates that the system should permit a "smooth" and [...]
The system can be operated in 3 different modes (see requirements A4, A5, A6, B1, B9, C1, C5, C10 and [...]
14/09/2015
38
On page 4 of the technical specifications, it indicates that the system must permit a "smooth" and automatic [...]
An electromechanical switch is allowed as there is no negative impact for the technical requirements.
14/09/2015
39
In the document "Draft Contract supply and maintenance" on page 11 section II.1.7, relative point (a) [...]
By derogation to the provisions of the article II.1.7. "General provisions concerning supplies", the [...]
15/09/2015
40
Is it possible to participate in the tender as contractor and also being subcontractor for other contender [...]
Yes, providing that this situation does not hinder, limit or distort competition. The Contracting Authority [...]
17/09/2015
41
The file "EN-7-05 GridBOC Annex 1 to Technical Specifications lot 2.pdf" should refer to the site of [...]
This is because the headquarter of the IET institute is in Petten, The Netherlands. This is just for [...]
21/09/2015
42
Regarding to the air conditioning system for the battery container, Is it possible to place the condensation [...]
Yes, as far as it respects the safety standards.
21/09/2015
43
In the tender document (EN-07-05 GRIDBOC Technical specifications Lot 2.pdf) figure 1 is shown the laboratory [...]
This supply does not include the SCADA system. The communication protocols supported by our SCADA system [...]
21/09/2015
44
According to the responses we have already received, the control system (PCS, transformer and parallel [...]
For lot 2, the size of the room that will host the control systems is shown in the Annex 1. However, [...]
22/09/2015
45
Dear Sirs, we need to know you VAT Number for deliveries to European Commission, Joint Research Centre [...]
Whereas the Commission is, as a general rule, exempt from all taxes and duties (including VAT) (see article [...]
22/09/2015
46
With reference to the procedure in question, herein, we request one week extension of the deadline for [...]
At this stage is not possible to extend the deadline for tender submission. The deadline for tender submission [...]
23/09/2015
47
With reference to the procurement procedure in question, we would like to have clarification on the definition [...]
Economic operators can submit a tender either as a sole tenderer or as partners in a consortium (with [...]
23/09/2015
48
At the point 6 in the Annex I of the contract it indicates that the system must have the CE Marking or [...]
The requirement "E6: CE Marking or equivalent" shall be read as "E6: CE Marking", as the equivalence [...]
23/09/2015
49
Please confirm that any kind of civil works are excluded.
We confirm that any civil works are excluded.
24/09/2015
50
Please confirm that the route of the cable already exists, and if so, can you indicate the path? Do you [...]
In respect to the DC cable that connects the outdoor unit with the indoor unit we will indicate the path [...]
24/09/2015