4
|
Please clarify if the deadline of 14 September is actually valid for both - offers and requests to participate [...]
|
The deadline of 14 September specified in the Contract Notice is the deadline to submit the technical [...]
|
07/09/2015
|
|
2
|
The point D 14 page 6 refers to the “control unit”. The ‘control unit’ shall be understood as the supervisor [...]
|
The control unit shall be able to connect to a SCADA system. Some specifications of the SCADA are available [...]
|
07/09/2015
|
|
3
|
At the point D14 page 6 is defined the container in which the batteries will be installed, but it is [...]
|
The AC/DC converter must not be in the same container with the batteries. The container is located outside [...]
|
07/09/2015
|
|
1
|
The point C9 page 6 refers on the containment system: container 20 ft. Is it possible to use even systems [...]
|
20 ft container is the maximum dimension, there is no problem by using a smaller container if the security [...]
|
07/09/2015
|
|
5
|
Where is it possible to find the Contract Notice and the templates of the administrative documents to [...]
|
On the site ‘'Ted - eTendering' please go to section ‘TED’. At the top, almost centrally there is a link [...]
|
07/09/2015
|
|
6
|
Question 1: In respect to the documents to be provided by the tenderer, including by the “sub-contractor [...]
|
1. Subcontractors shall submit the same documents as the main contractor; the document in copy for the [...]
|
07/09/2015
|
|
22
|
In the document “technical specification” on page 10 section 4 paragraph 1, it specifies that the delivery [...]
|
For both lots: Following a review of the technical specifications, we inform you that the delivery time [...]
|
09/09/2015
|
|
21
|
Therefore also the sub-contractors must submit: - cover letter - declaration of honor - document issued [...]
|
For both lots: Subcontractors identified as per heading III.1.3 of the Contract Notice must provide a [...]
|
09/09/2015
|
|
7
|
Question: In the document “Technical specifications” on page 8, third point, it refers to a range between [...]
|
The unit of measurement is VAR and not VOLTS. The correct values are -60kVAR < Q < +60kVAR for [...]
|
07/09/2015
|
|
8
|
Question: In the document “Technical Specifications” on page 8, point 7th, it is defined a complete cycle [...]
|
For the lot 1 the correct value is 150 KWh and not 1 MWh. For the lot 2 the correct value is 450 KWh [...]
|
07/09/2015
|
|