Results per page: 10 | 25 | 50 43 Preguntas found, displaying 1 to 25.[First/Prev] 1, 2 [Next/Last]
# Pregunta Respuesta Fecha de la última publicación Estado
1
- On page 25 of the Terms of Reference, the "Simulated Request for Services 1" lists two alternative [...]
Contact points must be provided for the EU countries which are not covered by the tenderer's project [...]
22/05/2017
2
In the terms of reference and on the list of "Annexes to the tender specifications", Annex X is mentioned [...]
Annex X has been added.
23/05/2017
3
We have noticed that all the section references mentioned in the Annex VIII (Document check list) don't [...]
Document updated
24/05/2017
4
We understand that Annex VII has to be calculated on the cumulated values for the last two years for [...]
Annex VII should be provided for the last year for which accounts have been closed. Paragraph: Tenderers [...]
24/05/2017
5
We understand that the CV do not have to be signed. Are we correct?
CVs shall be presented in accordance with the Commission recommendation on a common European format for [...]
24/05/2017
6
On page 20 of the ToR, it is mentioned that six (6) values and five (5) ratios should be calculated. [...]
Once you fill in the values in the first tab of the excel file "Simplified presentation" the scores are [...]
24/05/2017
7
Please advise if there is a targeted page limit for each hypothetical case study description
Tender Specifications, page 25: Each simulated exercise should be of maximum 30 pages.
24/05/2017
8
Reference is made to Section 3.6.B – Criterion B.1 of the Tender Specifications. Both the contract manager [...]
Yes, it can be any type of fact finding work that covers at least 15 member states.
29/05/2017
9
Dear Sir/Madam, - On page 25 of the Terms of Reference, the "Simulated Request for Services 1" lists [...]
In order to allow fair comparison, please provide a technical proposal on the second study only: "Study [...]
29/05/2017
10
Re the "Simulated Request for Services 1" for Lot 2 ‘Study supporting the impact assessment on food waste [...]
Question9
29/05/2017
11
On page 25 of the Tender Specifications, it is mentioned in the column referring to the Simulated Request [...]
Question9
29/05/2017
12
Dear Sir/Madam, We urgently need an answer concerning the question below (sent on 23.05.2017) as we would [...]
Question9
29/05/2017
13
Re the "Simulated Request for Services 2" for Lot 1 - ‘Study supporting the impact assessment on joint [...]
Indeed, tenderers should prepare a proposal assuming a new package of policy options. Tenderers should [...]
29/05/2017
14
Re the "Simulated Request for Services 2" for Lot 2 ‘Study supporting the impact assessment on food waste [...]
Indeed, tenderers should prepare a proposal assuming a new package of policy options. Tenderers should [...]
29/05/2017
15
Reference is made to Section 1.2 - Participation of the Tender Specifications. We understand that the [...]
If during the implementation of the FWC an amendment is necessary, this will be dealt in line with the [...]
30/05/2017
16
Please clarify if organisations established in the United Kingdom can participate in a consortium applying [...]
Organisations established in the UK can participate in this tender.
30/05/2017
17
To our understanding, it is possible to include subcontractors who provide eligible references or experts [...]
It is possible to include subcontractors who provide eligible references or experts in line with point [...]
30/05/2017
18
It is mentioned in page 21 of the Tender Specifications that the tenderer must provide references delivered [...]
The tenderer should provide references of projects delivered and not ongoing. To allow for a clear cut [...]
30/05/2017
19
To our understanding a subcontractor is not required to complete the excel file (available in the document [...]
The subcontractor is not required to send the excel file on simplified presentation viability. Subcontractors [...]
01/06/2017
20
Could you confirm if the proof of timely submission is the date of postage via courier service of applicants [...]
As indicated in the invitation to tender "Receipt is understood as the time at which the tenderer hands [...]
02/06/2017
21
To our understanding the core team can include experts who are not in-house / permanent staff of the [...]
The selection criteria relating to the team delivering the service are described in section 3.6.B. of [...]
02/06/2017
22
Following the clarification provided on "Subject: financial capacity of subcontractors " , to our understanding [...]
The CVs of experts are evaluated as part of the selection criteria relating to the team delivering the [...]
02/06/2017
23
Dear DG Santé, we would like to enquire into the deadline of the proposal. Unless we missed a prior information [...]
A corrigendum will be soon published that will extend the deadline from 19/6 to 26/6.
06/06/2017
24
Noting that clarification was provided on the dummy bid requirements on 29 May and that these are very [...]
Question23
06/06/2017
25
We consider that the given deadline of one month for this complex Framework Contract is very tight. In [...]
Question23
06/06/2017