Informaciones de las convocatorias de concurso

The time limit for receipt of tenders has been extended to 25/05/2020 at 23:59 CET
Título:
Prestación de servicios para el tablero de mandos y las herramientas de análisis...
Poder adjudicador:
European Investment Fund
Fecha de publicación del TED:
28/04/2020
Fecha límite de recepción de las ofertas:
25/05/2020
Estado:
Cerrada
Mostrar los parámetros del filtro

Results per page: 10 | 25 | 50 61 Preguntas found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4, 5, 6, 7 [Next/Last]
# Pregunta Respuesta Fecha de la última publicación Estado
61
Looking at the current situation with the huge COVID impact, the size of the RFP, the several questions [...]
Unfortunately, due to the tight deadline with regard to the planned contract signature, it is not possible [...]
14/05/2020
60
On payment schedule and terms (annex 6), do you have preference on monthly or quarterly invoice?
The EIF has preference for quarterly invoices.
14/05/2020
59
Would you consider accepting that the EIF receives the results of the penetration tests performed by [...]
The penetration test must be performed by a third party company. The results from a test performed by [...]
14/05/2020
58
Are the penalties the exclusive remedy of the EIF in case the SLA are not met ?
Penalties are always the last resort situation to a never improving situation (based on simple service [...]
14/05/2020
57
In pages 13 and p18 annex 4, it is mentioned that penalties can apply in case SLAs are not met. To which [...]
The fees will be applied on the quarterly invoices for the platform hosting fees.
14/05/2020
56
"In clause 6.1. Key personnel requirements and management (p19) from annex 4, it is mentioned : ""In [...]
This will apply to all the services provided from an EU-28 countries.
14/05/2020
55
Can we do perform some activities outside the EU (non-EU citizens), as soon as these activities don't [...]
Activities shall be performed from one of the EU-28 countries. Any of the Service Provider’s staff allocated [...]
14/05/2020
54
Referring to page 8 of the annex 4, diagram 2: What is the legend applying to dotted lines and plain [...]
There is a graphical error and basically there is no difference in meaning between dotted and plain lines [...]
14/05/2020
53
For the provision of the cloud environment, are we ok to consider that the standard terms and conditions [...]
The standard terms and conditions of the cloud provider shall be applicable upon the EIF.
14/05/2020
52
Is EIF covering independently the cloud costs (e.g. AWS or Azure) or should they be included in our proposal [...]
The cloud costs should be including in the proposal as EIF will not directly contract with the hosting [...]
14/05/2020