13
|
As concerns the legal and regulatory capacity: given that a) in section VII question 5 a. of the declaration [...]
|
We confirm that, as there is no selection criteria related to ‘legal and regulatory capacity’, a tenderer [...]
|
24/10/2018
|
|
10
|
Could the Commission specify if for both the Annual General Assembly of the Network of Copernicus Relays [...]
|
The case study mentions that "Both meetings should be organised back-to-back in order to facilitate logistics [...]
|
08/10/2018
|
|
12
|
Could you please clarify level of detail in which necessary information should be provided? Amount of [...]
|
"Evidence of the technical and professional capacity of the providers involved in the tender may be furnished [...]
|
22/10/2018
|
|
11
|
Could you specify what information should be provided regarding „description of the measures employed [...]
|
The call for tender states that "Evidence of the technical and professional capacity of the providers [...]
|
22/10/2018
|
|
8
|
In the description of Lot 2 (p. 9 - 11), three tasks are described "Evaluating the benefits of Copernicus [...]
|
The experience in managing these various methodologies will be checked in the selection criteria (chapter [...]
|
08/10/2018
|
|
6
|
Is it possible to avoid submitting documentary evidence requested in annex 6.1 if such documents (isued [...]
|
The tender specification state that "If evidence has already been provided for another procurement procedure [...]
|
01/10/2018
|
|
7
|
The case study is requiring to assess the different Copernicus user uptake communication activities ( [...]
|
The tenderer states that “The evaluation shall in particular include: (…) A quantitative estimate of [...]
|
08/10/2018
|
|
2
|
The e-submission form has a section called ‘Legal and regulatory capacity’. Which documents would need [...]
|
As there is no selection criteria related to "legal or regulatory capacity", the tenderers do not need [...]
|
19/09/2018
|
|
9
|
The tender specification explains in 4.1.4 that "The technical proposal is a detailed offer for the relevant [...]
|
The documents to provide evidence of the financial, economic, technical and professional capacity are [...]
|
08/10/2018
|
|
1
|
The tender specifications page 31 state that all tenderers shall provide proof of their economic and [...]
|
We confirm that sub-contractors shall not provide proof of their economic and financial capacity. However [...]
|
19/09/2018
|
|