Results per page: 10 | 25 | 50 9 Küsimused found, displaying all Küsimused .
# Küsimus Vastus Viimati avaldatud: Olek
9
Can you confirm that a company that has presence in 25 countries in the world can be considered as an [...]
Please describe your services and the company in your proposal and it will be the evaluation committee [...]
30/05/2013
8
On page 4 of service contract, it states that the payment of the balance will be due upon on receiving [...]
It's the final project report (three paper copies and an electronic version in MS-Word 2010 and pdf formats [...]
30/05/2013
7
On page 13 point 6 of TOR states: “The developed RT shall allow operation of an externally-written program [...]
The purpose of allowing operation of an externally written script is to provide a potential for automation [...]
30/05/2013
6
On section “Technical and professional capacity criteria and evidence”, on page 6 of TOR, it states: [...]
The purpose of this criteria is to ensure that potential contractors have sufficient experience in delivering [...]
30/05/2013
5
On page 12 point 10 of TOR states: “The EEA review secretariat shall be able to manage the workflow of [...]
“Manage the workflow” means that the secretariat can reassign a task to another user in case the previous [...]
30/05/2013
4
On Page 6 of the ToR you request that the Tender must prove that they have: experience in developing [...]
The purpose of this criterion is to ensure that tenderers have sufficient technical and professional [...]
27/05/2013
3
The provided link to the separate excel table in Annex 6 to the Tender Specifications- Financial Capacity [...]
It should now work. You can always find the Annexes to our tenders on the DG CLIMA tenders page at http [...]
14/05/2013
2
You answered that the guidance suggests we would not be able to provide the Annex 6. That is not the [...]
You correctly read that Annex 6 should not be filled in by public bodies. Please send in financial statements [...]
03/05/2013
1
The guidance says that the above has to be provided by means of Annex 6. Annex 6 states that public bodies [...]
Please note that under 2.3.1 of the specifications it states "In the event that the tenderer - for valid [...]
02/05/2013