# Küsimus Vastus Viimati avaldatud: Olek
14
Section 4.4 of Annex 7 specifies that Vector products should be thematically attributed with a range [...]
Firstly, all features that can help and are deemed relevant to ensure that for future change detection [...]
13/08/2019
13
While section 4.6 of Annex 7 specifies a general CLC+ backbone thematic accuracy of 90 %, section 4.4.1 [...]
One specification does not exclude the other, but in this case, section 4.4.1 of Annex 7 provides further [...]
13/08/2019
12
What is exactly meant with the award criteria “Completeness and the level of detail of the workflow information [...]
In essence all elements of information that are essential to be able to reproduce the process and obtain [...]
13/08/2019
11
Which is the date of reference in case of changing areas?
In principle, the reference year is 2018 for the satellite input imagery, and as closely as possible [...]
13/08/2019
10
Which texture parameter is expected from the VHR coverage?
It is up to tenderers to choose the most suited texture parameter to improve the classification.
13/08/2019
9
As the use of VHR2018 is mandatory in the CLC + production, will it be supplied to process the pilot [...]
Yes, the VHR2018 coverage will be available for CLC+ Backbone.
13/08/2019
8
In page 11 it is stated that only the management of the processing and storage shall be taken into account [...]
The EEA is currently assessing options for a CLMS wide processing, storage and delivery platform (such [...]
13/08/2019
7
Section 1.4.8 of the Tender Specifications asks that “national projection products, where those are part [...]
National projection products are considered an integral part of production and are expected as deliverables [...]
12/08/2019
6
Could you please confirm if we understood the following correctly? 1. We need to create an account on [...]
You are right in your assumptions in both instances.
12/08/2019
5
The exclusion criteria do not state any exclusion of EAGLE group members. Can you please clarify whether [...]
It is not possible at this stage to give a definite answer. The decision of whether to reject a tenderer [...]
12/08/2019