16
PC's MANAGEMENT SOFTWARE • Is the software for PC’s management (connected to the internal network of [...]
The EIB will provide the software necessary to manage the Laptops and PCs delivered by the Bank.
09/06/2017
15
IMAGE • How many images will need be managed ?
We do not expected to have more than 2 images as the EIB is aiming to work with the lowest possible number [...]
09/06/2017
14
PC's AND LAPTOPS REPLACEMENT • In the RFP, every 3 years the Provider needs to upgrade all PC’s / laptops [...]
At the EIB, PCs and laptops of key users are normally replaced after 3 years. The goal of this requirement [...]
09/06/2017
13
FLEXIBILITY In the RFP: the Tenderer shall offer the opportunity to increase or reduce the scope of the [...]
Neither a minimum nor a maximum are defined. The requested flexibility is expected not to exceed 10%. [...]
09/06/2017
12
KPI’s • Can you please provide EIB’s expected KPI’s ?
As the KPIs are dependent on the proposed solution, it is expected that the exact list of KPIs will be [...]
09/06/2017
11
TECHNICAL RESOURCE(S) DEDICATED TO THE MAINTENANCE OF THE RECOVERY SOLUTION • Who manages the Resource [...]
The task management of the Technical Resource(s) will be done by EIB. The Technical Resource will mainly [...]
09/06/2017
10
PACKAGES For a good understanding, please confirm : • Package 1 : EIB provides all IT equipment and all [...]
Service Package 1: EIB will provide all IT equipment and furniture. Service Package 2: The provider has [...]
09/06/2017
9
CONTRACT DURATION Please confirm : is this a 3-year contract which can be renewed (at the end of the [...]
Yes, this is correct.
09/06/2017
8
PRODUCTION DATE In the RFP, starting date of the production phase : 01/10/2017. Considering this is an [...]
The current contract runs until 31st December 2017. Therefore the starting date of the new contract in [...]
09/06/2017
7
AGENDA: Could you detail the timetable of the RFP? For example schedule of:  the commercial discussion [...]
Below is just an indicative timetable of the process after the opening of tenders: - Evaluation of tenders [...]