19
|
Shall subcontractors provide evidence regarding economic and financial capacity as well as technical [...]
|
The statement of subcontracting needs to be completed by the Tenderers and in this statement, reference [...]
|
04/06/2020
|
|
18
|
We kindly ask you to confirm that PRICE1 has to be intended as the total price for developing the Academy [...]
|
In section “13. Price” of the Tender Specifications the prices for the “Provision of services in support [...]
|
04/06/2020
|
|
17
|
Please confirm that the Legal Entity Form will be submitted by the group leader and partners, but not [...]
|
Indeed the Legal Entity Forms are for the tenderers (group representative for groups). The subcontractors [...]
|
29/05/2020
|
|
16
|
Shall the tenderers provide evidence concerning the exclusion situations described in points from (a) [...]
|
The supporting evidence has to be provided in accordance with section VI of the Declaration of Honour [...]
|
29/05/2020
|
|
15
|
Due the complexity of the requirements and the aim to deliver a valuable answer, we would like to kindly [...]
|
Please refer to Q 6 and its answer published on the 25th of May 2020 - an extension would not be provided [...]
|
29/05/2020
|
|
14
|
Could you please clarify whether SMEs, whose specific technical knowledge is not covered by the MTE, [...]
|
For tasks being assigned through a specific contract, which might need the employment of additional SMEs [...]
|
29/05/2020
|
|
13
|
Will off-the-shelf content be provided specifically to maritime domain technical/curricula skills or [...]
|
"Paragraph 2.4.3 is covering the requirements for Brokering a training course. The Courses brokered on [...]
|
29/05/2020
|
|
12
|
Will the MTE be participating as sole Subject Matter Expert in the development on learning courses and [...]
|
The Maritime Training Expert (MTE) shall be part of the contractor’s team during the development phase [...]
|
29/05/2020
|
|
11
|
If it is impossible to present a CV that meets all the criteria defined for a given project role, is [...]
|
Unfortunately your proposed solution cannot be accepted. For the selection criteria section, including [...]
|
29/05/2020
|
|
10
|
“To prove their technical and professional capacity concerning the standards ‘a’ and ‘b’ mentioned above [...]
|
Please refer to Question 2 and its Answer published on the 12/05/2020.
|
25/05/2020
|
|