11
|
• Confirmation of the type / level of IT and communication equipment currently provided by the contractor [...]
|
As stated in the tender specifications, section 1.1.4.2, all the necessary IT and communication equipment [...]
|
21/09/2016
|
|
10
|
Please can EDA provide: • Confirmation of the period of notice that would be given for any required Ad [...]
|
The period of notice will be mutually agreed between EDA and the Contractor and will be commensurate [...]
|
21/09/2016
|
|
9
|
It is noted in Technical Support 1.1.3.1 that the contractor is responsible for equipment maintenance [...]
|
A copy of the inventory of the technical equipment within the simulator facility is being provided to [...]
|
21/09/2016
|
|
8
|
Furthermore, is the contractor expected to forecast within the proposal any upgrade or enhancement work [...]
|
The technical proposal is to include a proposed methodology for identifying enhancements/upgrades. The [...]
|
21/09/2016
|
|
7
|
It is understood that the EDA Helicopter Programmes have been running for a few years now. Is there a [...]
|
“It is for tenderers to assess whether the TUPE is applicable or not. The tasks executed under the ongoing [...]
|
21/09/2016
|
|
6
|
There is a responsibility to maintain the fabric of the facility and to properly understand what is there [...]
|
As stated in the tender specifications, section 1.1.3.2, the equipment within the simulators building [...]
|
21/09/2016
|
|
5
|
Please can EDA provide: • Confirmation of the current course schedule for 2017. If this has not yet been [...]
|
As stated in the introduction to the technical specifications, the exact timings of each activity are [...]
|
21/09/2016
|
|
4
|
Please can EDA provide: A copy of the current course administrative instruction (as referenced in paragraph [...]
|
EDA will provide the course administrative instruction by e-mail to tenderers, following the submission [...]
|
21/09/2016
|
|
3
|
Please can EDA provide: A copy of the EDA Travel Guidelines (as referenced in paragraph 1.2.4.1 of the [...]
|
The EDA Travel Guidelines will be provided to the Contractor. These are not considered necessary for [...]
|
21/09/2016
|
|
2
|
Please can EDA provide; • A copy of the inventory of the technical equipment within the simulator facility [...]
|
A copy of the inventory of the technical equipment within the simulator facility is being provided to [...]
|
21/09/2016
|
|