35
With reference to section “3.2.3. Technical and Professional Capacity” of the Tender Specifications, [...]
The tenderer should submit the most relevant 3 references only.
05/02/2018
Répondu
34
With reference to section “2.2.7.3 Standby service” of the Tender Specifications, it is stated that “[...]
ECDC has a monitoring system in place that will send SMS alerts in case of system failure. The standby[...]
05/02/2018
Répondu
33
With reference to section “2.2.6.2 Minimum security measures by Contractor” of the Tender Specifications[...]
You are right, the correct reference is that each member of contractor’s staff will need to sign the [...]
05/02/2018
Répondu
32
With reference to content “8. List of Key performance indicators: Indicators for the work area ICT Backoffice[...]
Your understanding is correct. ECDC is using already the Microsoft System Center Operations Manager ([...]
05/02/2018
Répondu
31
With reference to section “3.2.3. Technical and Professional Capacity” of the Tender Specifications, [...]
The limit of 3 pages should be applied regardless if single economic operator or consortium.
05/02/2018
Répondu
30
The tenderer must submit proof of 3 relevant references to projects. Do you mean at least 3? And at most[...]
The tenderer should submit the most relevant 3 references only.
05/02/2018
Répondu
29
There is a limit of 3 pages for the description of the roadmap for the implementation of the security[...]
The page limit of 3 pages should be applied regardless if you have a single or multiple off-side locations[...]
05/02/2018
Répondu
28
There is a limit of 3 pages for the description of the tenderer's activity. In the case of a consortium[...]
The limit of 3 pages should be applied regardless if single economic operator or consortium.
05/02/2018
Répondu
27
The Tenderer is required to provide a document presenting the tenderer’s proposal for a Service Level[...]
Indeed chapter 1,2,4,5,6,7 of the draft SLA should be used without ANY modification. Indeed Chapter 3[...]
05/02/2018
Répondu
26
With reference to Section “3.2. Selection Criteria”. Could you please clarify whether relying on the [...]
Should any affiliated company be providing capacity to the tenderer to fulfil the selection criteria,[...]
05/02/2018
Répondu