18
|
Which supporting documents should be submitted together with the financial identification form?
|
The financial identification form must be signed and stamped by the tenderer's bank or a financial statement [...]
|
08/08/2013
|
|
6
|
Under task 3.3.1.1 Task 1.1. Setting a BEST working team, it is indicated that "a central BEST working [...]
|
The senior manager shall dedicate half of his/her time, so he/she is not expected to be full time like [...]
|
10/07/2013
|
|
21
|
Under point 2.3.1. the text reads: "In order to prove their economic and financial capacity, the tenderer [...]
|
No. According to 2.3, subcontractors whose intended share of the contract is equal to or above 20% of [...]
|
16/08/2013
|
|
20
|
Under point 2.3.1. the text reads: "In order to prove their economic and financial capacity, the tenderer [...]
|
If the share of subcontractor is equal to or above 20% of the value of the contract, 2.3.1 states that [...]
|
16/08/2013
|
|
16
|
The tender's specifications indicated that the team for Lot1 should include an expert in Biodiversity [...]
|
The tender specifications mention page 8 that " the team delivering the service should include, as a [...]
|
02/08/2013
|
|
10
|
The BEST call for tender is mentioning the development of "BEST strategies at the appropriate level - [...]
|
The list of deliverables on p24/25 of the tender specifications includes - inter alia - an item: "BEST [...]
|
16/07/2013
|
|
1
|
Point 1.1 of Tender Specifications says "Participation in this tender procedure is open to ..... and [...]
|
As you mentioned, the first paragraph of the tender specifications (1.1) deals with participation . In [...]
|
28/05/2013
|
|
23
|
On page 5-6 of the tender specifications, they said that "tenderers must provide the following information [...]
|
In order to prove their legal capacity and their status, all tenderers must provide a signed Legal Entity [...]
|
23/08/2013
|
|
7
|
It is indicated in the service contract notice that tenders will be opened on 16.9.2013 - 10:30 but nothing [...]
|
It is expected that the contract will be signed before the end of the year. However, there is no guarantee [...]
|
12/07/2013
|
|
9
|
Is the senior expert expected to demostrate past experience in EU ORs and OCTs like the biodiversity [...]
|
The senior expert is expected to demonstrate past experience in EU ORs and OCTs.
|
12/07/2013
|
|