35
|
a. ToR 4.2.1.2 Can we confirm the number of sites – EIB is a “multi-site campus” – how many distinct [...]
|
a. The EIB Group is currently in the process of renting several sites in the Kirchberg area of Luxembourg [...]
|
10/06/2016
|
|
34
|
In Annex 2 – there is a reference under Article 1 to “’requisite declaration (see Annex 2)…” we presume [...]
|
Your understanding is correct. This typo has been corrected and the document containing Annexes 2-4 has [...]
|
10/06/2016
|
|
33
|
It is unclear how many references are required for Lot 3 - is it only 5 OR only 3 OR total of 8?
|
Five (5) references of which three (3) relevant and verifiable references of assignments undertaken and [...]
|
10/06/2016
|
|
32
|
The Terms of Reference mention an "Appendix VI" (not Annex 6) several times - always in reference to [...]
|
Appendix VI in the Terms of Reference should read Annex 12 (CV Template). Tenders shall be evaluated [...]
|
10/06/2016
|
|
31
|
EIB states that they have the ambition of adopting an EMS - would this be ISO14001 compliant or similar [...]
|
As the EU Bank, the EIB Group would implement an EMS under EMAS, which in turn is based on the requirements [...]
|
10/06/2016
|
|
30
|
a. For all the emissions sources to be covered by the reporting, approximately how many different suppliers [...]
|
a. External supplier will be engaged by the appropriate internal EIB Group services. The main EIB Group [...]
|
10/06/2016
|
|
29
|
Regarding the curricula required as Annex 12, is is authorised to provide them according to the standard [...]
|
As stated in the Terms of Reference, "the use of the CV template attached as Annex 12 is mandatory."
|
09/06/2016
|
|
28
|
Since the tender is supposed to be handed in in English, could you please specify whether this also applies [...]
|
Official documents are to be provided in the original language. Tenderers are welcomed to provide translation [...]
|
09/06/2016
|
|
27
|
Could you please specify what "The relevance of the proposed approach vis a vis of successful references [...]
|
We will carefully assess the references of previous assignments against the proposed approach.
|
09/06/2016
|
|
26
|
Could you please specify what you consider "relevant experience" of team members?
|
Relevant to the services described in each lot. • Team/Project Leader - with at least 15 years of relevant [...]
|
09/06/2016
|
|