Detalji poziva na dostavu ponuda

Please note that the deadline for submission of tenders has been changed to 01/08/2018 and the deadline for request for clarifications to 24/07/2018
Naziv:
Usluge razvoja softvera
Javni naručitelj:
European Centre for Disease Prevention and Control (ECDC)
Datum objave na TED-u:
08/06/2018
Rok za primitak ponuda:
01/08/2018
Status:
Zatvoreno
Prikažite parametre filtriranja

Results per page: 10 | 25 | 50 136 Pitanja found, displaying 121 to 130.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14 [Next/Last]
# Pitanje Odgovor Posljednji datum objave Status
16
According to the tender requirements, the tenderer must present three relevant references. If the tenderer [...]
Please see the answer to question no 5. All references included in the offer must cover at least one [...]
20/06/2018
15
Section 1.5 addresses that we should indicate in our tender we should identify the subcontractors, the [...]
In regards to “1.5 Subcontracting” and the statement “Tenderers are required to identify subcontractors [...]
20/06/2018
14
We understand that the maximum number of references is three. Please confirm that our understanding is [...]
Please refer to the answer to Question No.5 Question5
19/06/2018
13
The document states that in case of a consortium each partner must present 3 separate references. We [...]
Please refer to the answer to Question No.5 Question5
19/06/2018
12
Could you please confirm our understanding that a joint offer of an consortia with 3 companies and 3 [...]
Please refer to the answer to Question No.5Question5
19/06/2018
11
Under the section Requirements, it is mentioned “the tenderer must present three relevant references [...]
Please refer to the answer to Question No.5. Question5
19/06/2018
10
Would it be possible for ECDC to prolong the tender period considering the amount of work needed to respond [...]
Considering that there is still a full month remaining until the deadline, we do not see an extension [...]
19/06/2018
9
Our understanding is that we can use our own template to submit the references. Could you please confirm [...]
Any template can be used for the references requested in “3.2.3 Technical and professional capacity” [...]
19/06/2018
8
We interpret 2.9.2 Estimation methodology to be agreed upon as part of the kick-off meeting hence not [...]
As stated in “4.1 Technical proposal”, the estimation methodology must be included in the “Service Delivery [...]
19/06/2018
7
In cell I43 od sheet "Financial Scenario" of the Financial proposal form, the extramural effort (cell [...]
Indeed a clerical mistake. An corrigendum of Annex II (Financial proposal) will be published shortly.
19/06/2018