12
|
In section I.11 (p. 16) of the tender document the estimated volume of services for Part 1 "Selection [...]
|
The actual volume of services related to Part 1 "Selection and assessment of candidates for senior management [...]
|
11/02/2019
|
|
11
|
- do all pages of the proposal document need to be signed or only the last page? - is an electronic signature [...]
|
By the expression “proposal document”, we believe that you mean the technical and financial tender. If [...]
|
07/02/2019
|
|
10
|
what does ‘year’ mean in the document contract? As there is also stated Start and dates of the contract [...]
|
In annex 6 “Declaration on supporting documents of selection criteria”, under point 2. “Supporting documents [...]
|
07/02/2019
|
|
9
|
Dear Sir or Madam, Our question pertains to section I.3.1.3 "Support and advice to selection panels": [...]
|
According to point I.3.1.3 of the Technical Specifications, the task of providing support and advice [...]
|
05/02/2019
|
|
8
|
Could you please confirm which is the correct reference number for this procurement procedure? The ITT [...]
|
The correct reference of this procedure is HR/R1/PO/2018/046 even though some documents of this call [...]
|
05/02/2019
|
|
7
|
Reading the tender specifications, it it seems like there is a difference between '360 feedback mechanism [...]
|
The term “multi-source feedback mechanism” is used as an overall definition for the different feedback [...]
|
05/02/2019
|
|
6
|
What is the expected overlap between candidates that join the assessment center, development program [...]
|
In terms of target group, there will be a certain overlap between the assessment centre, the development [...]
|
05/02/2019
|
|
5
|
Will there be a link between the outcomes in the 360-feedback and the participants in the development [...]
|
The development programme is a purely voluntary programme. Some participants in the multi-source feedback [...]
|
05/02/2019
|
|
4
|
Could you please share the existing Director General and Director job profiles including their required [...]
|
Under I.3.1.1 of the technical specifications, it is clearly stipulated that the assessment of managerial [...]
|
05/02/2019
|
|
3
|
How will candidates be selected for participation in the development programme?
|
Participation in the development programme is voluntary; selection will be based on individual interest [...]
|
05/02/2019
|
|