3
|
According to point 1.1 of tender specifications, "Participation in this tender procedure is open on equal [...]
|
Yes, on the condition that they can provide the necessary documentation and evidence required.
|
01/07/2013
|
|
4
|
According to the point 1.1 of the tender specifications, "Participation in this tender procedure is open [...]
|
The composition of the Steering Committee suggested in the tender specifications, including the representatives [...]
|
04/07/2013
|
|
5
|
Can you please confirm that an NGO registered in Switzerland is eligible for the tender ENV.B.2/SER/2013 [...]
|
The first paragraph of the tender specifications (1.1) deals with participation. In the footnote on the [...]
|
05/07/2013
|
|
17
|
Do tenderers have to submit also an electronic version of the offer on a CD?
|
As stated in the Invitation Letter page 2, "Tenders must be submitted as follows: one signed original [...]
|
08/08/2013
|
|
15
|
Do we need to send original administrative documents or scanned copies are enough? This question is especially [...]
|
If you are not in possession of the originals then scanned copies will suffice for the purpose of the [...]
|
01/08/2013
|
|
13
|
How many copies of tender have to be submitted?
|
Please see 4a) of the Invitation. "One signed original and two copies of your tender must be placed inside [...]
|
31/07/2013
|
|
11
|
If a tenderer presents an offer including LOT 1 and LOT 2 is it still possible to win one LOT if one [...]
|
As indicated on page 9 of the tender specifications: "Each LOT will be evaluated separately (...)".
|
29/07/2013
|
|
19
|
In a tender with one tenderer and mutiple sub-contractors, can a tenderer submit : a simplified balance [...]
|
Please see 2.3 which states "The evidence requested should be provided by each member of the group in [...]
|
16/08/2013
|
|
14
|
In section 2.4 Award criteria, points are only allocated to the quality of the proposed methodology ( [...]
|
The proposal will be evaluated based on 1. Quality of the proposed methodology; 2. Organisation of the [...]
|
31/07/2013
|
|
8
|
In the point 2.3.2.b on criteria of the team delivering service it is indicated that an expert in biodiversity [...]
|
The expert in biodiversity in EU Outermost Regions and Overseas Countries and Territories is expected [...]
|