Can referenced projects (presented for Section 2.3.3 a. Criteria relating to tenderers) cover multiple [...]
|
A delivered service/reference project can, if relevant, reply to more than 1 criterion.
|
29/08/2019
|
|
13
|
Can the same reference project be presented as the most important one in two different criteria? If yes [...]
|
A delivered service/reference project can, if relevant, be presented as the most important one for more [...]
|
10/09/2019
|
|
19
|
Could you please clarify which answer a subcontracting company should choose (YES / NO / N/A) in case [...]
|
As it is the COMBINED capacity of all tenderers and subcontractors that must comply with the criteria [...]
|
12/09/2019
|
|
17
|
Declaration on honour, p. 6, section: "The team delivering the service should include, as a minimum, [...]
|
Thanks for noticing. There is no specific reason, also this part of the declaration should have the choice [...]
|
11/09/2019
|
|
5
|
Do all the required reference projects have to be completed?
|
Yes, reference projects have to be completed.
|
29/08/2019
|
|
18
|
Does it have to be the same person who signs all the official documents, or can it be a different person [...]
|
It does not necessarily has to be the same person signing all the documents as long as the persons signing [...]
|
11/09/2019
|
|
3
|
Does the Letter of intent need to be signed by an authorized representative of the subcontracting company [...]
|
Yes indeed, the letter of intent needs to be signed by an authorized representative of the subcontracted [...]
|
28/08/2019
|
|
33
|
Good afternoon. What is the deadline hour on Monday? Thank you.
|
Dear Madam, dear Sir, According to the contract notice (section IV.2.2), the deadline to submit the tender [...]
|
23/09/2019
|
|
22
|
I'm urgently Looking for the requirements of the tender report - can you help with further informations [...]
|
The "tender report" is a document automatically generated from e-Submission and listing all the documents [...]
|
12/09/2019
|
|
20
|
In Annex 2 - Letter of Submission of Tender it is asked to fill the name of the "Person authorized to [...]
|
The Annex 2 - last page - must be signed by a person authorized to make binding offers to third parties [...]
|