# Pitanje Odgovor Posljednji datum objave Status
1
Bom Dia Pretendo marcar uma vista ao local da obra. Quando é possível ?
As per Point 12 of the Invitation to Tender, "To schedule an on-site visit, an e-mail shall be sent to [...]
07/01/2021
2
Must we present all the Documents requested in the Selection Criteria (14.3, 14.4, 14.5 and 14.6) for [...]
As per Point 9 of the Tender Specifications, "The tenderer must provide required evidence for the exclusion [...]
22/01/2021
11
We've still some clarifications request with no answer and due to the new answer deadline, it may means [...]
Please note that the deadline to reply submitted questions has been postponed to 29/01/2021 (6 days) [...]
22/01/2021
3
Are there any specific requirements for fencing and protect the working areas?
No specific requirements. The intervention areas must be clearly indicated, signposted and have a protection [...]
22/01/2021
4
Are there any specific requirements for the cleaning during the performance of the works?
No specific requirements. Given the sensitivity of the technical equipment and building installations [...]
22/01/2021
5
Regarding the Quantity Map (Articulado/MQT): - Art 5.2.3 e 5.2.4 : the units of measurement shouldn't [...]
We confirm that, in Art. 5.2.3 e 5.2.4 of Appendix 4, the unit should be “un” and not “m2”.
22/01/2021
6
Regarding the Quantity Map (Articulado/MQT): - Art 7.1.1.5 e 7.1.1.6: we request the identification of [...]
Art 7.1.1.5 is without alarm (instead of with alarm as announced), the identification is S04 / E4A (descendente [...]
22/01/2021
7
Regarding the Quantity Map (Articulado/MQT): - Art 8.1.12: The quantities of circular registers regulating [...]
The units in Art 8.1.12 of Appendix 4 should be 6 instead of 4. A new Art 8.12.a is also inserted: 8.1.12a [...]
22/01/2021
8
Regarding the Quantity Map (Articulado/MQT): -Art 8.1.25: Quantity vs dimension and location of the 4 [...]
In Art 8.1.25 of Appendix 4, the dimension to take into account shall be 45x45 cm instead of 50x50cm [...]
22/01/2021
9
Regarding the Quantity Map (Articulado/MQT): - Art 8.1: where is considered the work “Desmontagem cuidado [...]
The indicated item is not considered as necessary. Please follow the technical solution according to [...]
22/01/2021