42
|
Due to data protection law we cannot ask our clients to fill in nor sign the “Reference to similar contracts.doc [...]
|
The confirmation by the client of all information provided in the template “Reference to similar contracts [...]
|
19/09/2019
|
|
41
|
Is there something similar on EUIPO or do we have to create our own template and if so are there any [...]
|
There is no particular template for the technical proposal. The instructions for the presentation of [...]
|
17/09/2019
|
|
40
|
do we have to specify all aspects including courses on demand?
|
It is mandatory for each course to specify the following aspects according to the Annex II.2. Course [...]
|
16/09/2019
|
|
39
|
What happens if 80% of the courses proposed are subcontracted- do we have to have a own catalogue necessarily [...]
|
For both lots, the tenderer must submit a training catalogue which includes the list of courses to be [...]
|
16/09/2019
|
|
38
|
The RFO FP-QTM and the RFO-TM to be send wit the offer?
|
The implementation of the contract is described in Section 1.4 of the Annex 3 Draft Services Framework [...]
|
16/09/2019
|
|
37
|
In Annex 1 page 11 it appears that EUIPO requests "3 courses provided through a third party". Is the [...]
|
During the implementation of the contract, EUIPO can ask for specific courses not included in the Contractor [...]
|
16/09/2019
|
|
36
|
Buenos días, en la respuesta dada a la pregunta nº 5 de fecha 13/08/2019 indican que el volumen anual [...]
|
La propuesta económica no debe modificarse.
|
16/09/2019
|
|
35
|
Dear Sir/Madam, in the case of a joint tender is it necessary that both parties meet the 3 years of financial [...]
|
The minimum levels of economic and financial capacity must be met by the tendering group as a whole, [...]
|
16/09/2019
|
|
34
|
Is a consortium on entities eligible to participate in lot 2 if we have had a yearly turnover (all parties [...]
|
As indicated in the Annex I, the minimum yearly turnover requested for each lot must be met for the past [...]
|
16/09/2019
|
|
33
|
Buenos días, en el punto 13.3 del Anexo I indican que la propuesta técnica para el lote 2 debe incluir [...]
|
Por "actividades de aprendizaje respetuosas con el medio ambiente" (“environmentally friendly learning [...]
|
16/09/2019
|
|