17
As stated in the Terms of Reference that NON-KEY experts must not be asked to sign statements of exclusivity [...]
The same non-key experts can be presented in several offers.
17/09/2021
16
Dear Sirs, We have carefully analysed Article 5. of the Instructions to tenderers for the titled Project [...]
Following careful consideration of this question, in the interest of broadening the level of competition [...]
16/09/2021
15
After careful research, we have found that employees at the institutions of the beneficiary country ( [...]
It's tenderer's responsibility to check if employees at the institutions of the beneficiary country ( [...]
16/09/2021
14
As per the Terms of Reference point 6.1. Staff, would professors from the University of Sarajevo, specifically [...]
It's tenderer's responsibility to check if professors from the University of Sarajevo are considered [...]
16/09/2021
13
With regards to the Terms of Reference, Section 4.2.1: Specific activities, it states that Phase 2 would [...]
The indicative time-frame for confirmation by the Beneficiary of the list of faculties to be located [...]
16/09/2021
12
In part C. Declarations and other templates, Annex 7 (the Pre-Financing Guarantee Form) is mentioned [...]
Pre-Financing Guarantee should be submitted by a winning tenderer after the service contract is fully [...]
16/09/2021
11
Given that a large number of stakeholders are mentioned in the Terms of Reference such as the Contracting [...]
The Contracting Authority (i.e. EIB) is responsible for approving the reports and deliverables after [...]
16/09/2021
10
When proposing the team structure for other experts which are not key experts, is it possible to name [...]
Regarding non key experts, tenderers are free to propose a different team structure to the indicative [...]
16/09/2021
9
The Tender Documentation notes the time period as 12 months - 6 for Component 1 and 6 for Component 2 [...]
This question seems to be based on a misreading of the tender documentation whereby the bidder has simply [...]
16/09/2021
8
The RFP notes that no-one can submit a bid who has been involved in preparing this RFP. Given that the [...]
Although the RFP includes as an annex the study, ''Improving Sarajevo's Resilience Through Urban Regeneration [...]
16/09/2021