1. Do you already have aircrafts or UAVs in operation or should they will be offered here as well? 2. [...]
|
1. EMSA already has RPAS in operation as well as a new procurement for large size RPAS (EMSA/OP/1/2018 [...]
|
23/04/2018
|
|
10
|
a) Will EMSA please verify the SATCOM equipment the vendors propose for Lot 1, (2 Mbps data rate) is [...]
|
a) In principle both lots are intended for fixed wing RPAS. The Agency's current platforms are medium [...]
|
20/04/2018
|
|
41
|
Answer to the question 25: “The Satellite Service Provider shall assess which security requirements are [...]
|
There are no security requirements on teleport location or accreditation because the information to be [...]
|
08/05/2018
|
|
8
|
Are there alreary routers, and of which type, aboard the current fleet of RPAS ? Will it be the responsibility [...]
|
The Agency operates with different RPAS platforms, most of them already have routers on-board to distribute [...]
|
20/04/2018
|
|
27
|
Are we correct in understanding that we do not need to provide any evidence regarding the exclusion criteria [...]
|
With regard to Exclusion criteria the tenderers do not need to upload any documentary evidence for exclusion [...]
|
30/04/2018
|
|
9
|
As some French overseas territories are included in the EU territory according to international treaties [...]
|
As per Tender Specifications: 1.1.8 and Appendix 1: 2.1: Areas of operation can be all sea areas surrounding [...]
|
20/04/2018
|
|
5
|
Can the same company be subcontractor in more than one tender to the FWC?
|
Please refer to point 10 of the Tender Specifications - economic operators on the market are free to [...]
|
20/04/2018
|
|
7
|
Can you confirm: - The method used to evaluate the link availability (exclusions, periods of time to [...]
|
-The Bidders can select the method that they consider more suitable to evaluate the link availability [...]
|
20/04/2018
|
|
12
|
Concerning Appendix 1 point 2.4.: How many SATCOM terminals have to be provided for each size (medium [...]
|
There is no minimum nor maximum number of terminals that must be offered per category. Offers will be [...]
|
23/04/2018
|
|
11
|
Concerning point 15.4: what are the criteria adopted for assessing the financial capacity? What is the [...]
|
The basic method is the analysis of the tenderer’s annual accounts (or financial statements). The financial [...]
|