Ajánlati felhívás részletei

Cím:
IT-infrastruktúrával kapcsolatos szolgáltatások
Ajánlatkérő:
European Centre for Disease Prevention and Control (ECDC)
A TED-es közzététel dátuma:
20/12/2017
Az ajánlatok kézhezvételére vonatkozó határidő:
28/02/2018
Státusz:
Lezárt
Szűrési paraméterek mutatása

Results per page: 10 | 25 | 50 75 Kérdések found, displaying 21 to 30.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8 [Next/Last]
# Kérdés Válasz Legutóbbi közzététel dátuma Státusz
55
In KPI BO13(many is called the same) Every completed test must have a test report. Question 1: Can you [...]
Indeed the testing activities are described in 2.2.3.8 of the tender specifications.
13/02/2018
54
According to the answer to question 11, the team is to be described in the Service Delivery Plan. Should [...]
Sample CVs for each profile will be required for the technical and professional capacity. For the SDP [...]
13/02/2018
53
In 2.2.7.4 (tender specification) on site and off site work ECDC state that will be 4+1 seat however [...]
ECDC is currently moving to new premises and expect that 5 seats will be available for the suppliers [...]
13/02/2018
52
Are all the KPIs described in Chapter 8 measurable with existing ITSM tools?
Many KPIs, especially in the area of incident and request management, can be measured with the ITSM. [...]
13/02/2018
51
ECDC says it have some Printer MFP, Should the contractor cover hardware and maintenance of those as [...]
The contractor should NOT cover hardware and maintenance for the MFDs. That will be provided by the printer [...]
13/02/2018
50
In the event a tenderer (main contractor) intends working with one (or more) subcontractor(s) for the [...]
From the list of documents mentioned, you can provide for each subcontractor the 'LOI to Collaborate' [...]
09/02/2018
49
In section 3.2.3 (Technical and Professional Capacity) of the Tender Specifications, it is requested [...]
Your assumption is fully correct. The description of the tenderer's professional activity should be 3 [...]
09/02/2018
48
In answer 41, you wrote "The main intention is that (...) all the providers staff (...)". But in the [...]
Ideally we see all consultants here once in a while, but practically the positions required for local [...]
09/02/2018
47
Is SCOM the only System Management tool that is currently used at the Agency?
SCOM is the main tool for System monitoring. On addition we use Paessler in the networks area (and thus [...]
09/02/2018
46
P.32 of the Tender states that "The contractor shall have a defined and documented information security [...]
As mentioned in question #42: Indeed the ISMS should be submitted as part as the evidence for Technical [...]
09/02/2018