# Kérdés Válasz Legutóbbi közzététel dátuma Státusz
21
Dear Sirs You specify a 60 A4 page limit for the technical proposal; is this to include the requested [...]
The 60 DIN A4 pages is excluding CVs and project management information. Please also see question #18 [...]
10/05/2019
25
Here is a link provided in the ITT with reference to the HRLs [https://land.copernicus.eu/pan-european [...]
The requirement of "[...] (b) aligned to HRL files [...]" in sections 1.4.2.1.3 and 1.4.2.1.4 of the [...]
15/05/2019
24
To our understanding, the expected outputs shall be rasters for all tasks. How are these outputs expected [...]
It is correct that all outputs are raster files. The type of information provided within HR VPP will [...]
13/05/2019
26
From what is stated in this section, is it the output expected a WMS service?
Section 1.4.3 summarises the different type of data deliverables, not how files shall be disseminated [...]
15/05/2019
31
What is the expected number of users and/or volume of service use for the “Data dissemination/access” [...]
Copernicus land service currently counts nearly 40.000 registered users. Out of these, somewhat more [...]
21/05/2019
30
Section 1.4.2.1.1 mentions that the future contractor shall process a set of vegetation indices: is the [...]
Yes, the future contractor is expected to process all Sentinel 2 A/B files within the AoI (see section [...]
21/05/2019
32
In a joint consortium, where the lead member fulfills the requirements stated in section 2.2.2.2. would [...]
All members of a consortium must complete, sign and submit a simplified Financial Statement in accordance [...]
21/05/2019
33
The 5th bullet in chapter 1.4.2.1.7 (page 14) mentions one or two meetings (75-100 participants each) [...]
The future contractor will not be responsible for the logistics of the user meeting(s) mentioned in section [...]