# Domanda Risposta Data dell'ultima pubblicazione Stato
9
Section 2.3.2.2 request the bidders to provide a three experts in policy affairs and at least one of [...]
The full text of the tender specifications on this point reads: "Three experts in energy policy affairs [...]
18/09/2015
8
Article 2.3.2.2 request the contractor to provide two experts in business Intelligence, and at least [...]
Yes, a master in Renewable Energy covers this criteria.
18/09/2015
7
Article 2.3.2.3 of the Tender specifications (page 8) requests tenderers to provide a " List of minimum [...]
Yes, the minimum value refers to the overall value of the study/report.
10/09/2015
6
Article 2.3.2.3 of the Tender specifications (page 8) requests tenderers to provide a " List of minimum [...]
No, ongoing studies/reports are not eligible as a reference.
10/09/2015
5
Article 2.3.2.3 of the Tender specifications (page 8) requests tenderers to provide a " List of minimum [...]
No, interim reports cannot be accepted as evidence.
10/09/2015
4
Article 2.3.2.3 of the Tender specifications (page 8) requests tenderers to provide a " List of minimum [...]
If the reports of the studies/projects contain confidential information, the documents can be expunged [...]
10/09/2015
3
Article 2.3.2.2 request "One expert in web-design and web-maintenance: The expert should have a bachelor [...]
The expert should have a bachelor degree. The expert does not need specifically a degree in web-design [...]
04/09/2015
2
As per Article I.4 of the Draft Contract, the payment terms only includes two interim payments and the [...]
As indicated in article I.4 of the draft contract no pre-financing payment is foreseen.
04/09/2015
1
The Tender specification does not contain the template for the submission of the financial offer. Do [...]
As mentioned in the specifications: "The quoted price is all-inclusive and covers all the services to [...]
04/09/2015