21
With reference to section “8.List of Key Performance Indicators” of “EN-Technical Annex 4 Draft SLA” [...]
You are right that the reference is wrong, as the list of contract managers is now in the document “EN-Technical[...]
01/02/2018
Risposto
22
With reference to Technical Annex 3 – Consultancy Profiles, there are descriptions for the profiles of[...]
Indeed your understanding is correct and Front Office System Administrator is equal to FrontOffice administrator[...]
01/02/2018
Risposto
23
With reference to “2.2.7.3 Standby service” of the “EN-Tender Specifications_9196_IT_Infrastructure services[...]
The standby duty service is always performed in full calendar weeks. As mentioned under 2.2.7.1 ECDC [...]
01/02/2018
Risposto
24
With reference to Section “3.2.1. Legal Capacity” of the Tender Specifications, the Tenderer shall provide[...]
All the members of the Consortium should provide Legal Entity form, as they will be jointly liable for[...]
05/02/2018
Risposto
25
With reference to Section “1.5. Subcontracting”, it is our understanding that in case that subcontracting[...]
If the tenderer relies on the subcontractors to fulfil the selection criteria, these subcontractors must[...]
05/02/2018
Risposto
26
With reference to Section “3.2. Selection Criteria”. Could you please clarify whether relying on the [...]
Should any affiliated company be providing capacity to the tenderer to fulfil the selection criteria,[...]
05/02/2018
Risposto
27
The Tenderer is required to provide a document presenting the tenderer’s proposal for a Service Level[...]
Indeed chapter 1,2,4,5,6,7 of the draft SLA should be used without ANY modification. Indeed Chapter 3[...]
05/02/2018
Risposto
28
There is a limit of 3 pages for the description of the tenderer's activity. In the case of a consortium[...]
The limit of 3 pages should be applied regardless if single economic operator or consortium.
05/02/2018
Risposto
29
There is a limit of 3 pages for the description of the roadmap for the implementation of the security[...]
The page limit of 3 pages should be applied regardless if you have a single or multiple off-side locations[...]
05/02/2018
Risposto
30
The tenderer must submit proof of 3 relevant references to projects. Do you mean at least 3? And at most[...]
The tenderer should submit the most relevant 3 references only.
05/02/2018
Risposto