Išsami informacija apie kvietimą pateikti pasiūlymus

Antraštė:
AO 10658 Parengiamosios žiniasklaidos, spausdinimo ir daugiakanalės paslaugos
Perkančioji organizacija:
Publications Office of the European Union (OP)
TED publikavimo data:
15/03/2017
Pasiūlymų priėmimo terminas:
19/04/2017
Būsena:
Užbaigta
Rodyti filtro parametrus

Results per page: 10 | 25 | 50 31 Klausimai found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4 [Next/Last]
# Klausimas Atsakymas Naujausio paskelbimo data Būsena
31
POD 233 - Variable costs - Print finish - Lamination ... In the variable cost of laminating we have the [...]
1. Different tasks have been grouped together in order to reduce the number of price items. On average [...]
07/04/2017
30
Do you confirm that there is no Parf requested for lot 3?
There are no separate documents required for lot 3. Please see the requirements for lots 1 and 2 (point [...]
07/04/2017
29
LOT 3 Will MOST orders include a combination of graphic design + Printing services (thus the contractor [...]
Orders on lot 3 will always be a combination of premedia/multichannel and printing services (see point [...]
07/04/2017
28
1. When arranging the PDF, according to the instructions from the specifications, the initial text will [...]
1. The layout of the created PDF should be the basis for the other formats. 2. The table of contents [...]
07/04/2017
27
You provided meta data (ISBN, ISSN, DOI) for EPUB. How should we proceed with meta data for the xml files [...]
There will be no additional metadata provided. Dummy content can be used for metadata that is deemed [...]
07/04/2017
26
How did you determine the total values of orders per lot before the launch of the call for tenders?
It is an estimation that is derived from an internal analysis of project cost calculations during the [...]
07/04/2017
25
Do the totals of estimation forms for lots 1 + 2 + 3 roughly equal to the total values of orders?
The totals of estimation forms of the three lots reflect the Publications Office’s best estimation of [...]
07/04/2017
24
Why is it for the variable and fixed costs T = print run = 1450?
For variable costs 14650 is used as an estimated average print run per project. For fixed costs 5 is [...]
07/04/2017
23
POG 2001 to POG 2011 are listed in Technical Annex IV. In the price schedule, however, we only find POG [...]
The price schedules and estimation forms are correct. There is a mistake in Technical Annex IV. The only [...]
06/04/2017
22
It seems that the ISBN code isn't complete in the new technical annex provided.
The excel version of the same document has been uploaded into the Document Library, displaying correctly [...]
05/04/2017