Results per page: 10 | 25 | 50 12 Klausimai found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Klausimas Atsakymas Naujausio paskelbimo data Būsena
12
Annex 1 of the tender specification contains a list of documents to be submitted including naming conventions [...]
We can confirm that the submission needs to provide evidence against all the technical criteria, as also [...]
08/09/2020
11
We understand that during the framework contract implementation it might be necessary that contractors [...]
We can acknowledge the request for confirmation. When the Commission requests offers for specific work [...]
28/08/2020
10
As a UK based company we understand that our eligibility as a joint tenderer under the framework may [...]
It is not possible to novate an on-going contract with a different company regardless of its ownership [...]
25/08/2020
9
Is it sufficient to highlight that the projects we are submitting for T1 - T7 have been in English, to [...]
Normally that should be considered sufficient.
25/08/2020
8
In addition to listing our access to testing facilities what other evidence do you require? Could you [...]
In order for us to put the relevant access information into context, it has to be explained what the [...]
25/08/2020
7
Could you please elaborate on what is meant by "A list of the principal services provided in the past [...]
For this Criterion T8 the tenderer is indeed asked to show that it has a track record of consultations [...]
25/08/2020
6
For the CVs and projects required per the selection criteria, is it required to have 3 unique CVs and [...]
Over criteria T1 to T7, the 3 unique projects may be the same in each separate criterion, i.e. in theory [...]
25/08/2020
5
The two tables in Annex 6 have two separate sets of requirements for staff qualification grade bands [...]
The financial proposal should contain both tables of Annex 6. The first table is related to the case [...]
24/08/2020
4
The links on page 11 to studies on vehicle safety and on the automotive sector do not seem valid. Are [...]
Thank you for noticing this issue. Indeed, the text and links are: 1.4.3.2. Examples of previous studies [...]
11/08/2020
3
Could the Contracting Authority provide Word format of the annexes included in the Technical Specifications [...]
A Word format of the annexes has been uploaded.
23/07/2020