9
|
According to section III.4.3.1 of the Tender Specifications, the tender response requires a CV for a [...]
|
Unfortunately, there is a clerical mistake in the Selection Criteria Questionnaire (EN-1-07) as the correct [...]
|
30/04/2019
|
|
8
|
As per Invitation to tender 1. Submission of tenders: Will a tender submitted by organisation that was [...]
|
Indeed, any person who knows the PIC number of a company and has an EU login can submit a tender for [...]
|
30/04/2019
|
|
6
|
AS per Tender Specifications III.4.3.1 Criterion 1 - capacity to provide a contract manager, specifically [...]
|
With regards to "Tender Specifications III.4.3.1 Criterion 1" fields like accounting, linguistics, translation [...]
|
24/04/2019
|
|
4
|
As regards the profiles required as per Terms of Reference: Can one of the two proposed Project Managers [...]
|
The role of the Contract Manager can be fulfilled by one of the two proposed Project Managers if the [...]
|
24/04/2019
|
|
11
|
Can you confirm what is the deadline for having sent the hand signed originals by? The Invitation for [...]
|
Correct. Having in mind that the deadline for submission of tenders is 15 May 2019, the hand-signed originals [...]
|
07/05/2019
|
|
13
|
Can you please confirm that the documents must be signed phisically and not electronically? in case pf [...]
|
Correct. As stated in the Invitation to tender, the following documents must be sent in original: • Declaration [...]
|
07/05/2019
|
|
3
|
Could EIOPA give an indication of the anticipated contract award date?
|
As the contract award is subject to several factors, including unpredictable circumstances which are [...]
|
24/04/2019
|
|
7
|
Could you kindly advise on electronic tender submission requirement. Namely: To prepare and submit a [...]
|
If access to the existing account is no longer possible for declared PICs, there are 2 different steps [...]
|
30/04/2019
|
|
2
|
Does this contract replace the one called Germany-Frankfurt-on-Main: Service provision for XBRL-related [...]
|
The multiple framework contract signed following the publication of Contract Notice 2014/S 158-283581 [...]
|
12/04/2019
|
|
15
|
In tab Scenario, Total amount for four years (to be used for the financial evaluation): this amount can [...]
|
Correct. Please also consult the answer to Question10
|
10/05/2019
|
|
12
|
In Technical Evaluation Questionnaire Annex EN-1-08, when the answer to a technical question includes [...]
|
Correct, by analogy the tables will be excluded from the maximum page limit if requested explicitly in [...]
|
07/05/2019
|
|
1
|
In the tecnical evaluation questionnaire (EN-1-08), section III (Questions), question 1 calls for the [...]
|
Correct, this means 2 XBRL Taxonomy Development Experts.
|
10/04/2019
|
|
5
|
Is there a maximum page limit and/or a prescribed document format for Contractor's documents supporting [...]
|
There is no maximum page limit and/or a prescribed document format for Contractor's documents supporting [...]
|
24/04/2019
|
|
14
|
Please confirm that in tab Financial Offer the price rates to complete are daily rates, that mean the [...]
|
Correct
|
10/05/2019
|
|
10
|
The estimated total value of the services for the entire duration of the framework contract is 4,160,300 [...]
|
As per II.1.4 and II.1.5 of the Tender Specifications, the estimated total value of the services for [...]
|
30/04/2019
|
|