Results per page: 10 | 25 | 50 7 Mistoqsijiet found, displaying all Mistoqsijiet .
# Mistoqsija It-tweġiba Data tal-aħħar pubblikazzjoni L-istatus
1
The current locally based Euraxess representatives (ER) have a very important expertise, which is also [...]
Your understanding is correct. According to point 2.4.2 of the tender specification “Subcontracting is [...]
13/03/2023
2
You state in Annex 7 to 'Develop an overall strategy (of not more than 8 pages) for: An overall programme [...]
The whole case study as described in Annex 7 should not exceed 8 pages. This space should be enough to [...]
22/03/2023
3
Due to the Easter holidays (both Catholic and Orthodox), and the complexity of the tender’s requirements [...]
The Easter period has been taken into account for the calculation of the submission deadline. Therefore [...]
12/04/2023
4
Dear Sir, Madam, Given the upcoming Catholic and Orthodox Easter holidays, could you please consider [...]
Please see our answer to question 3.
12/04/2023
5
Can you provide with a two (2) weeks deadline extension?
The submission deadline was calculated in a way to allow enough time for preparation of strong tenders [...]
12/04/2023
6
You clearly state in I.5.2 Price revision index - Price revision is not applicable to this FWC. Please [...]
While preparing the tender documents, the Contracting Authority duly assessed the use of price revision [...]
12/04/2023
7
In the price schedule excel sheet you include 220 person/days per year for the Project Coordinator. However [...]
The team at the central level must be composed of one Project Coordinator and at least of one Quality [...]
14/04/2023