10
|
This question is referred to the section where the Declaration of honour should be included. While reading [...]
|
The Declaration of honour is part of the administrative proposal.
|
03/10/2014
|
|
11
|
It is stated that either the lead contractor and the sub-contractors (share>20%) should provide the [...]
|
Supporting documents to the Declaration of Honour are not required at this stage
|
03/10/2014
|
|
9
|
Work Package 2- page 9 states the following. " The contractor has to liaise with the host organization [...]
|
The potential host should be an institution which can provide a suitable venue at their premises or premises [...]
|
03/10/2014
|
|
8
|
We understand that the criteria of price (low cost) in the evaluation of this tender is very high (at [...]
|
As specified in the tender specifications (ToR) 1.4 - Scope and description of tasks, number of participants [...]
|
03/10/2014
|
|
7
|
Please can you confirm the exact time of day when the submissions are due to be submitted on the 8th [...]
|
As per the invitation letter, tenders sent by registered mail or by courier should be sent not later [...]
|
01/10/2014
|
|
6
|
According to Annex 2 of the Specifications (Letter to submit tender), the tenderers are required to provide [...]
|
Yes, the table "Breakdown of tasks and fees against team members" should be filled in. It should be noted [...]
|
01/10/2014
|
|
5
|
The Specifications mention that the number of participants in each laboratory will by between 50 and [...]
|
As specified in the tender specifications point 1.4 - Scope and description of tasks, number of participants [...]
|
25/09/2014
|
|
4
|
We have some added value proposals for the tender, but as we have a budget constriction, please confirm [...]
|
The offer should be in line with the tender specifications and the price should not exceed the estimated [...]
|
24/09/2014
|
|
3
|
Please confirm if the balance payment will be done after the second lab or if the payment will be done [...]
|
The payment will be done at the end of all activities. The contracting authority will make the payment [...]
|
24/09/2014
|
|
2
|
The tender documents include a Technical Tender Form in annex 4. We understand that we have to fulfil [...]
|
Yes, tenderers should fill in and submit Annex 4. However it is not the main document to explain the [...]
|
24/09/2014
|
|