It-titlu:
Appoġġ lill-Ministeru Bulgaru għall-Ambjent u l-Ilma bl-Appoġġ fl-Implimentazzjo...
L-Awtorità li Qiegħda Toħroġ il-Kuntratt:
European Investment Bank (EIB)
Id-data tal-pubblikazzjoni tat-TED:
19/04/2019
Limitu ta' żmien għall-wasla tal-offerti:
12/06/2019
L-istatus:
Magħluq
Uri l-Parametri tal-Iffiltrar

Results per page: 10 | 25 | 50 13 Mistoqsijiet found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Mistoqsija It-tweġiba Data tal-aħħar pubblikazzjoni L-istatus
1
We are interested in submitting a proposal for this tender. However and due to several holidays during [...]
The time limit for receipt of tenders or requests to participate was extended to 12/06/2019 at 23:59CET [...]
16/05/2019
3
Dear Madam, Sir, Request you to provide the payment schedule for the project. Could you confirm if the [...]
According to the Terms of Reference, Clause 7.1 Reporting requirements it is mentioned that “Progress [...]
22/05/2019
4
Dear Sirs, Could you please clarify if experience in the field of public procurement as per EU regulations [...]
It is clarified that experience in the application of the Practical guide to contract procedures for [...]
22/05/2019
10
Здравейте! Бихме искали да попитаме дали е правилно нашето разбиране, че изискуемата сума от 500 000 [...]
Please refer to a previous answer: Question2
22/05/2019
12
Здравейте! Относно образованието на ключов експерт 3 - Key Expert 3: Project Management Expert, се изисква [...]
Please refer to previous answer: Question5
24/05/2019
2
It is written that "..The candidate (individual company or consortium altogether) has implemented, during [...]
We hereby clarify that each of the projects presented as references shall be of a minimum value of EUR [...]
21/05/2019
5
Hello! Concerning the qualification requirements to Key Expert 3: Project Management Expert, it is written [...]
A Bachelor’s Degree in the fields related to Project Management and additional five (5) years of General [...]
22/05/2019
6
Are there status reports available about the actual implementation rate (%) of acievements for non EU [...]
The applications from the water operators to MA are under evaluation and negotiations. No fixed number [...]
22/05/2019
13
Hello! It is not clear how the experts will be evaluated. It is said in the Instructions that "Experts [...]
It is clarified that the exact less or additional points, to the 80% of the maximum points to be scored [...]
24/05/2019
7
We noticed a small inconstancy between p. 6 and 7. p. 6 §4.1.1 Task 2. « during the quarterly meetings [...]
The text in the Terms of Reference, p. 7 §4.1.1 Task 2, instead of: Instead of : • TASK 2: Upon request [...]
22/05/2019