90
|
EIB mentions: •“The external offices which currently have MPLS connectivity are mandatory for the successful [...]
|
MPLS connectivity is mandatory for the locations listed as mandatory. If the Tenderer cannot propose [...]
|
07/09/2016
|
|
89
|
Article 11 of the Model Framework Agreement allows EIB to suspend the Agreement or Pending Contracts [...]
|
According to Article 11 of the Model Framework Agreement, Service Provider is not entitled to compensation [...]
|
07/09/2016
|
|
88
|
Does the Deed of Undertaking bind the Bidder to sign the Framework Agreement and the Contract, or just [...]
|
We refer to Section 4 Contracting Modalities of Annex 5 - Terms of Reference. We also refer to Article [...]
|
07/09/2016
|
|
87
|
Will EIB award the successful Bidder one Contract (defined term) per Lot rather than individual Contracts [...]
|
We refer to Section 4 Contracting Modalities of Annex 5 - Terms of Reference. We also refer to Article [...]
|
07/09/2016
|
|
86
|
This question was created by EIB following the site visits: Is it allowed to drill new entries into the [...]
|
Drilling new fiber entries into the building is not forbidden, but it needs to be reviewed and approved [...]
|
01/08/2016
|
|
85
|
This question was created by EIB following the site visit: What are the cable lengths from building entries [...]
|
WKI fibre entry Floor 1 To Switch Room WKI Floor 0 - approximately 270m EKI fibre entry Floor 4 To Switch [...]
|
01/08/2016
|
|
84
|
This question was created by EIB following the site visit: Shall the internal cabling inside EIB buildings [...]
|
Yes, the internal cabling inside EIB buildings has to be entirely delivered (including supply of cable [...]
|
01/08/2016
|
|
83
|
We plan to use in country local access circuit providers for connectivity of the EIB site to our infrastructure [...]
|
Yes, the local access circuit providers are considered subcontractors, in accordance with section 4.3.2 [...]
|
01/08/2016
|
|
82
|
This relates to 4.3.2 Subcontracting (Annex 5). For lot 2 the successful company will have relationships [...]
|
EIB's permission for the subcontractor's replacement is required for all subcontractors on which the [...]
|
01/08/2016
|
|
81
|
Given the level of work and analysis required to provide a complete and detailed response, and that responses [...]
|
The EIB is considering an extension of the submission deadline. Further information will be publicly [...]
|
01/08/2016
|
|