Regarding the Work Hypotheses in Annex V, please can you confirm what you expect to see from this? Is [...]
|
The work hypotheses in annex V is a business case that serves the contracting authority to evaluate part [...]
|
20/02/2019
|
|
7
|
PRINCE2 material is available in Danish, Dutch, French, German, Norwegian and Polish as well as English [...]
|
The text refers to the language of the manuals, not to the language of the delivery of the training. [...]
|
20/02/2019
|
|
6
|
If the tenderer considers bidding for both lots, does it have to present 2 technical proposals? For example [...]
|
If the tenderer considers bidding for both lots, it has to present 2 technical proposals, one for each [...]
|
20/02/2019
|
|
5
|
Do you consider subcontractors, as third parties? And if so, they need to complete the Third Party File [...]
|
Subcontractors are not contractual parties and therefore they do not have to submit the Third Party File [...]
|
20/02/2019
|
|
4
|
Regarding Annex Va. Technical Award Criteria, page 2, Criteria 2: Management of the Service, point 7: [...]
|
Tender proposal will be evaluated based on the consistency with the requirements set in the tender documentation [...]
|
15/02/2019
|
|
3
|
The Subcontracting Information form contains a table to specify subcontractors' details. Could you please [...]
|
Tenderers must indicate the percentage of the value of the contract that they intend to subcontract to [...]
|
15/02/2019
|
|
2
|
Could you please verify/check the total number of students for Annex V.b.4 Work Hypothesis Lot 2? The [...]
|
Please refer to corrigendum 1
|
15/02/2019
|
|
1
|
To whom it may concern, Regarding the list of major similar contracts (Annex I, page 8), the timings [...]
|
As indicated in point 13.2.2 of the Annex I “Tender Specifications”, to be taken into consideration, [...]
|