58
|
After the contractor organises the matchmaking, it is described that the Contractor will supervise the [...]
|
Please refer to the reply to question no 56. An extension to the deadline cannot be granted.
|
10/05/2022
|
|
57
|
First of all, it is described that ECFIN applies the first pre-screening, followed by the Contracting [...]
|
In line with Design Task 2 “Clarification and eligibility review of request” the Contracting authority [...]
|
10/05/2022
|
|
56
|
Accordingly, after the contractor organises the matchmaking, it is described that the Contractor will [...]
|
Annex 9 point 8 states that the Advisory Assignment fiche is signed only by the beneficiary and the expert [...]
|
10/05/2022
|
|
55
|
Based on step 10: Expert submits interim and final reports to Contractor. Contractor verifies performance [...]
|
Please note that annex 9 serves as illustration. The experts’ cost and expenses shall be paid by the [...]
|
10/05/2022
|
|
54
|
Evidence notes that we must provide CVs and documents proving required level of education. What exactly [...]
|
Yes, this is correct. Documents supporting the level of relevant education include: copies of diploma [...]
|
10/05/2022
|
|
53
|
Is it possible to indicate or estimate the number of service requests for Lot 1? Can we assume that there [...]
|
Yes, it can be assumed that for each assignment there will be a separate service request. The reference [...]
|
10/05/2022
|
|
52
|
Can you please clarify and confirm what is the payment arrangement for the Contractor in Lot 1? Based [...]
|
Please refer to reply to Question44.
|
10/05/2022
|
|
51
|
We make reference to the replies to questions 5, 10, 19 and 21. Considering the limit of 15.000 words [...]
|
As explained in the answers to questions 5, 10, 19 and 21, the limit of 15,000 words prevails for the [...]
|
10/05/2022
|
|
50
|
Dear Sir/Madam, due to the holidays around both the Orthodox and Catholic Easter and the related disruptions [...]
|
Please be informed that no extension will be granted to the submission deadline.
|
10/05/2022
|
|
49
|
We make reference to the reply #33 on the scoping for Lot 1. Although the Framing Document is optional [...]
|
With reference to the answer provided to Q33, please note that the optional Framing Document is provided [...]
|
10/05/2022
|
|