28
The price quoted in the financial annex can only be indicative since there are details such as location [...]
The prices quoted in the financial tender annex will become part of the framework contract and will be [...]
12/11/2018
Beantwoord
27
Could you please specify what do the multiplication factors in the financial proposal form refer to? [...]
The multiplication factors listed in the financial proposal forms are specific to each lot. They are [...]
09/11/2018
Beantwoord
26
If a company is selected and asked to provide an offer on a specific event, can additional experts, who [...]
Additional experts can be added to the team at a later date, if required. However, the experts must also [...]
09/11/2018
Beantwoord
25
In section 3.2.2. of the tender specification you say that "the Simplified Financial Statement must be [...]
You can indeed upload two separate documents (one Annex VI for each subcontractor). If the tenderer does [...]
08/11/2018
Beantwoord
24
In Lot 4 do you foresee the contractor or ECDC undertaking logistics such as issuing joining instructions [...]
The logistics in Lot 4 such as issuing joining instructions to participants, creating delegate paperwork [...]
08/11/2018
Beantwoord
23
The Financial proposal form for 4b and 4c requests a price for exercise delivery in the case of a 1 day [...]
For Lot 4 all prices (such as the costs for the scenario, exercise documentation and reporting) should [...]
07/11/2018
Beantwoord
22
Should the original signed documents be send by post within the same deadline of the online application [...]
Signed originals are not required as part of the submission of a tender. Only electronic submissions [...]
07/11/2018
Beantwoord
21
Could you please clarify if there is a difference between subcontractors and consultants?
A third party contracted by the contractor, such as a consultant who is not a member of the contractor [...]
07/11/2018
Beantwoord
20
Could you please clarify if subcontractors are individuals or institutions (such as universities)?
Third parties contracted by the contractor are considered to be subcontractors, whether they be individuals [...]
07/11/2018
Beantwoord
19
Evidence A1 for Lots 1, 2 and 3 specifies that the tenderer must provide references for projects delivered [...]
Yes, a summary of relevant projects should be provided. This should include, but is not limited to, references [...]