Szczegóły ogłoszenia o przetargu

Tytuł:
Korzyści zdrowotne i społeczne z ochrony przyrody i różnorodności biologicznej
Instytucja zamawiająca:
European Commission, DG ENV+CLIMA
Data publikacji w witrynie TED:
24/07/2014
Termin nadsyłania ofert:
17/09/2014
Status:
Zamknięte
Pokaż parametry filtra

Results per page: 10 | 25 | 50 11 Pytania found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Pytanie Odpowiedź Data ostatniej publikacji Status
11
The tender requires running a 2 day stakeholder workshop in Brussels. According to the tender “The Commission [...]
Provision of the venue will include audio-visual and other technical and personnel support although the [...]
11/09/2014
10
Could you please specify where the workshop is expected to take place? Thanks in advance.
The workshop is expected to take place in Brussels
11/09/2014
9
Further to question 8. The reply does not answer my question. Maybe I was not clear. I try again: Some [...]
The PANDOR system is not used in Directorates-General Environment and Climate Action. For this tender [...]
11/09/2014
8
The majority of the requested paperwork is already uploaded on PADOR, which the commission can access [...]
All these Annexes can be found in Word format on our tenders page on Europa: http://ec.europa.eu/environment [...]
08/09/2014
7
Regarding participation in Green Week 2015, would it be possible to obtain more information about expectations [...]
The format for Green Week workshops is normally for a 1.5 hour session with 2-4 speakers and/or panel [...]
05/09/2014
6
When is the workshop expected to take place? Could this be at a later stage (towards the end of the project [...]
The workshop is expected to take place towards the end of the contract. Its timing should allow for the [...]
26/08/2014
5
Does taking part in Green Week involve sending a member of the team to Green Week to present the preliminary [...]
The contractor will need to ensure sufficient representation to assist with the foreseen workshop at [...]
26/08/2014
4
For task 4 are the participation in Green Week and the workshop entirely separate activities?
Under Task 4 it is clearly stated that the contractor "will provide documentation and will take part [...]
22/08/2014
3
We would like to submit a well-structured timetable for the work and would be grateful if we could have [...]
The contract must be awarded before the end of 2014 and it is expected that the signing of the contract [...]
18/08/2014
2
Good morning. Do you have any criteria on the limitations of the budget regarding direct and indirect [...]
The Commission does not require tenderers to provide information concerning the over-head costs. These [...]
08/08/2014