Informações relativas ao concurso

Título:
Prestação de serviços SATCOM para o RPAS
Entidade adjudicante:
European Maritime Safety Agency
Data de publicação na TED:
31/03/2018
Prazo para a receção de propostas:
21/05/2018
Estado:
Encerrado
Mostrar parâmetros do filtro

Results per page: 10 | 25 | 50 45 Questões found, displaying 1 to 25.[First/Prev] 1, 2 [Next/Last]
# Questão Resposta Data da última publicação Estado
45
One of the aero antenna available on the market has a size of 45.7cm. Will it be acceptable to offer [...]
As per point 2.4 of Appendix 1 Technical Specifications the antenna equivalent diameter for large size [...]
15/05/2018
44
Several bidders are requesting an extension of time to answer to the tender. Indeed the complexity of [...]
EMSA understands the complexity of the tender and for that reason already foresaw a bid submission period [...]
15/05/2018
43
In order to ensure a fair competition with the current SATCOM Service Provider (having the best inside [...]
EMSA understands the complexity of the tender and for that reason already foresaw a bid submission period [...]
08/05/2018
42
With reference to the second bullet point in paragraph 8.1.2 in the Tender Specification document (EN [...]
Until now the provision of SATCOM services for the RPAS was a responsibility of the RPAS Services Providers [...]
08/05/2018
41
Answer to the question 25: “The Satellite Service Provider shall assess which security requirements are [...]
There are no security requirements on teleport location or accreditation because the information to be [...]
08/05/2018
40
We would like to kindly request an extension of the bidding deadline, taking into consideration the special [...]
EMSA understands the complexity of the tender and for that reason already foresaw a bid submission period [...]
08/05/2018
39
During the set-up phase, the SATCOM capacity provision must be made available to the RPAS Services Providers [...]
The minimum of 100 flight hours is an estimation in order to guarantee the readiness of the system, not [...]
08/05/2018
38
In the "Template for Financial Offer", Lot 1 and Lot 2 sheets, is cell E18 value a ceiling for price [...]
The value of cell E18 is the data volume consumption per month used for the purpose of the calculation [...]
08/05/2018
37
Please kindly clarify if Turkey is among the eligible countries mentioned in Article 19 of the Invitation [...]
Only companies which are established in a member state of the Union or one of the other states listed [...]
07/05/2018
36
We have noted that on price grids for Lot1 and Lot2, the volume of Gb consumption per month has not been [...]
In Appendix 3 Financial Technical Template only the blank cells need to be filled in by the Bidders. [...]
07/05/2018
35
could you please clarify if the on-ground compliance tests will be paid to the Bidder, and shall be therefore [...]
The on-ground compliance test shall take place following the dispatch of the contract award letter and [...]
07/05/2018
34
The tender requires a test before signing of the FWC. Also, the SATCOM terminal to be used for the on-ground [...]
As indicated in point 5.1.3 of Appendix 1 Technical Specifications the SATCOM terminal to be used for [...]
07/05/2018
32
For Lot 1 and Lot 2, the Tender Specifications requires the contractor to provide a price per-unit rate [...]
In Appendix 3 Financial Tender Template for Lot 1 and Lot 2 there is no minimum commitment for data volumen [...]
07/05/2018
33
For Lot 1 and Lot 2, shall the VSAT terminal be part of the scope of our service (terminal leasing) or [...]
Lot 1 and Lot 2 are intended for SATCOM services provision for RPAS; a Specific Contract (SC) for these [...]
07/05/2018
31
In Lot 3, for the installation of the VSAT terminal in land sites, we would require a clarification regarding [...]
The VSAT terminal antenna in-land will be installed at the aerodrome or airport hosting the LGCS. Prior [...]
07/05/2018
30
In Lot 3, Tender Specifications requires the Contractor to install and configure all the hardware and [...]
If the VSAT antenna needs to be place on a vessel, EMSA could use their own vessels or contract vessels [...]
07/05/2018
29
In I.6.1 is is stated "the contractor is responsible to determine and ensure that the correct methodology [...]
The provision of SATCOM services is an eligible supply of telecommunications, broadcasting and electronic [...]
07/05/2018
28
In order to be able to evaluate our responsibilities, could you please confirm that the relevant RPAS [...]
The RPAS are equipped with an autonomous waypoint driven control system for take-off, landing and in-flight [...]
07/05/2018
27
Are we correct in understanding that we do not need to provide any evidence regarding the exclusion criteria [...]
With regard to Exclusion criteria the tenderers do not need to upload any documentary evidence for exclusion [...]
30/04/2018
26
Due to the current social context in France, some key suppliers are impacted by the ongoing strikes. [...]
EMSA understands the complexity of the tender and for that reason already foresaw a bid submission period [...]
30/04/2018
25
§1.1.8: Could you please confirm that the teleports must be located in an EU country for security reason [...]
In the Tender Specifications there are no requirements on the location, the level of accreditation and [...]
30/04/2018
24
§6.1.2: Where will take place the integration of SATCOM antenna on the RPAS?
The installation of the SATCOM terminal on the RPAS is an activity that shall be covered by the terminal [...]
30/04/2018
23
§2.4: Will the customer have a router integrated in each RPAS? If yes, could you please specify the brand [...]
EMSA operates with different RPAS platforms,those meant to be operated beyond Radio line of Sight already [...]
30/04/2018
22
§1.2.4: Could you please provide the delivery point for the VSAT equipment? To EMSA premise? Or at the [...]
The delivery point for the VSAT equipment will be the place of the RPAS mission location as indicated [...]
30/04/2018
21
§1.1.2: Could you please indicate the customer POP where all the traffic should be delivered?
The POP where all the traffic should be delivered will be the Local Ground Control Station (LGCS) that [...]
30/04/2018