14
|
Can you please confirm that the experts category B3 – Experts in rail expertise should instead read B4 [...]
|
Confirmed. It should be read as follows B1 - Project Manager: At least 10 years' experience in project [...]
|
20/08/2018
|
|
13
|
Regarding Evidence A1, there is no indication concerning the number of references expected. Is there [...]
|
The applicants must deliver as many references as they think can be enought to prove their capability [...]
|
20/08/2018
|
|
12
|
If the scope of work of a project covers more than one technical and professional capacity criterion, [...]
|
Yes, it can be acceptable. The applicant is reminded to clearly identify in its application which criterion [...]
|
20/08/2018
|
|
11
|
We believe the ERA is an important party for the success of this study. Can you please clarify if DG [...]
|
DG Move will support coordination between ERA and the contractor, nevertheless it can not be held responsible [...]
|
20/08/2018
|
|
10
|
Can you please clarify if the mentioned business case refer to the opportunity costs/benefits resulting [...]
|
It refers to the opportunity costs/benefits resulting from an accelerated deployment for IMs, operators [...]
|
20/08/2018
|
|
9
|
The fourth bullet mentions “infrastructure investments”. Can you please confirm that these investments [...]
|
Broadly yes, though there may be other participants in investments on certain infrastructures e.g. infrastructure [...]
|
20/08/2018
|
|
8
|
Since the railway lines comprising the Core Network Corridors and the Rail Freight Corridors are in some [...]
|
As outlined in Section 2.3 a task of the study is to select and determine 3 networks focussed on Core [...]
|
20/08/2018
|
|
7
|
In order to continue to stage 3 “Tender data”, the following attachments are requested: - Legal and regulatory [...]
|
Q1: What are the requirements to prove the legal and regulatory capacity? Legal and regulatory capacity [...]
|
09/08/2018
|
|
6
|
Please confirm if in “Tender Data”, all the parts of the proposal (A-F) have to be included in separate [...]
|
Part E: Financial offer, must be in a separated file from the other parts. The part A to D and F could [...]
|
03/08/2018
|
|
5
|
According to tender documents, Part C shall cover the elements included in section 4.2 Selection criteria [...]
|
It is acceptable to make reference to Part B.
|
03/08/2018
|
|