Informações relativas ao concurso

Título:
Estudo sobre arquitetura de sistemas de uma Infraestrutura de Comunicação Quantu...
Entidade adjudicante:
European Commission, DG for Communications Networks, Content and Technology (CON...
Data de publicação na TED:
23/09/2019
Prazo para a receção de propostas:
04/11/2019
Estado:
Encerrado
Mostrar parâmetros do filtro

Results per page: 10 | 25 | 50 27 Questões found, displaying 1 to 10.[First/Prev] 1, 2, 3 [Next/Last]
# Questão Resposta Data da última publicação Estado
27
In order to tell the transportation company that will bring the letter; would it be possible to get a [...]
See following: Postal address: European Commission DG CONNECT R2 – Budget & Finance BU25 04/115 Jaana [...]
04/11/2019
26
Would it be acceptable for the EU to have 2 subcontractors which annexes 4 and 6a are loaded without [...]
Please request subcontractors to sign the documents and provide them by e-mail. There is no possibility [...]
29/10/2019
25
on the e-submission guide it is said : "If you consider the tender complete and ready for submission, [...]
It has to be person(s) authorised legally representing the company (same person who has signed the Annex [...]
29/10/2019
24
Could you please let us know if a recent trade register excerpt is accepted as Notice of appointment [...]
If the name of the legal representative is clearly mentioned in the notice of an appointment, this document [...]
28/10/2019
23
Criterion B10 requires: "Collectively the team of at least 10 people should have knowledge of the EU [...]
For each EU Member State having signed the EU QCI, in the team suggested for carrying out the tasks there [...]
28/10/2019
22
Can you please tell us if it is required to provide the below inputs at the submission stage: “The Contractor [...]
It is not needed at the submission stage. The aspects linked to the SAL (security aspect letter) will [...]
28/10/2019
21
Is it necessary to provide evidence of the compliance with “environmental, social and labour law……Directive [...]
This is included in the Annex IV: Declaration of honour. No additional documentation needed.
28/10/2019
20
The tender specifications say that subcontractors must complete Annex 4 if (1) their share of the contract [...]
We confirm that it is all selection criteria's listed under sections 4.2.2, 4.2.3 and 4.2.4 in the tender [...]
23/10/2019
19
Can you confirm the evidence described in Chapter VI of the Annex 4 at the top of the page 39 (a recent [...]
This is required only from the tenderer for whom the contract is awarded.
23/10/2019
18
Chapter VII of Annex 4 requests the tenderer to declare they comply to the selection criteria applicable [...]
The filling of the Annex IV is done individually per economical operator participating to the call declaring [...]
23/10/2019