a. How many users will need to have access to those systems on Commission’s behalf? b. Please, confirm [...]
|
A: See reply to question #37 B: Regular monitoring of the helpdesk's activities will be ensured by the [...]
|
12/11/2018
|
|
59
|
According to Annex 2, we understand that for the Level I, II and III CVs the university degree is not [...]
|
See reply to question 58
|
21/11/2018
|
|
65
|
According to the answer 61: "All experts defined in Annex II (Qualification levels I to IV) will hold [...]
|
See replies to questions 30 and 31
|
29/11/2018
|
|
76
|
According to the specification of the CfT, there appear two different sets of reports: (Section 1.2.4 [...]
|
Both lists are correct and complement each other. Section 1.2.4 explains delivery from the payments perspective [...]
|
10/12/2018
|
|
3
|
According to the Tender Specifications, we need to provide references in English, German, French, Italian [...]
|
The evidence to fulfil criterion A2 consists of references for actions (projects or services) delivered [...]
|
02/10/2018
|
|
23
|
According to the Tenderer Specifications, we need to provide references showing the provision of helpdesk [...]
|
Please see reply to question #10
|
12/10/2018
|
|
10
|
According to the Tenderer Specifications, we need to provide references showing the provision of helpdesk [...]
|
The tenderer must provide references showing the provision of helpdesk services. Only services provided [...]
|
05/10/2018
|
|
26
|
According to the tendering specifications we read that all the evidence concern the Selection Criteria [...]
|
The tenders must be presented as follows (section 1.6): Part A: Identification of the tenderer Part B [...]
|
12/10/2018
|
|
44
|
Can the contracting authority confirm alternative contact methods are funded separately by them or should [...]
|
The Contracting Authority expects the future Contractor to provide equivalent contact services to the [...]
|
07/11/2018
|
|
40
|
Can the Contracting Authority explain how access to the JIRA based ticketing system will be provided [...]
|
The Contracting Authority will provide the Contractor with the necessary credentials (username and password [...]
|
06/11/2018
|
|