Informações relativas ao concurso

Título:
Sistema de transporte inteligente cooperativo da autoridade de certificação de r...
Entidade adjudicante:
European Commission, Joint Research Centre - Ispra (JRC-IPR)
Data de publicação na TED:
19/04/2019
Prazo para a receção de propostas:
07/08/2019
Estado:
Encerrado
Ocultar parâmetros do filtro
Parâmetros do filtro


Results per page: 10 | 25 | 50 95 Questões found, displaying 61 to 70.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8, 9, 10 [Next/Last]
# Questão Resposta Data da última publicação Estado
35
Following is written in clause II.6.3: The contractor is liable for any loss or damage caused to the [...]
With reference to Article II.6.3. we confirm that the "total amount of the contract" does refer to the [...]
20/06/2019
1
Dear, Could you make the documents available for download, as I can only see the Invitation Letter? Kind [...]
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
4
Dear Sirs, Please indicate the section of the Call from tender from where we could download the following [...]
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
27
Could you please provide the percentage breakdown of fixed and mobile C-ITS stations?
The percentage breakdown is not defined at this moment as it will depend on the market demand. It is [...]
20/06/2019
30
Could you please provide the number of C-ITS station types?
This is not defined at this moment as it is based on market supply of C-ITS stations.
20/06/2019
29
Could you please provide the number of 'of end-entities’ subscriber organisations?
This is not defined at this moment as it is based on market demand. It is foreseen that the Specific [...]
20/06/2019
31
Could you please provide the definition of "compliance assessment criteria"
Compliance/conformity assessment is to be interpreted as defined in the main part of the C-ITS Delegated [...]
20/06/2019
21
Could you please indicate the maximum number of Authorisation Tickets (Certificates) in case that the [...]
CORRIGENDUM: INSTEAD OF 'Annex I - Part 2: Technical Specifications does not define a maximum amount [...]
20/06/2019
13
Could you please indicate the duration of the meetings?
The duration of the meetings are not expected to last more than 1 (one) working day per face to face [...]
19/06/2019
49
Could you please explain the reason why C equals 5 for WKP2 of Phase 1 and equals 10 for WKP2 of Phase [...]
The constant C was considered to take into account the specific situation in WKP/phase. Please, see the [...]
20/06/2019